15351 W ERWIN ST 91411
Certificate Information: 15351 W ERWIN ST 91411
- Application / Permit
- 21014-20000-05578
- Plan Check / Job No.
- B21VN15254
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 34'4" X 14' 8" ADDITION AND CONVERSION OF (E) GARAGE TO ADU. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofO Issued on 4/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2021 | PINANK PATEL |
| Corrections Issued | 11/19/2021 | PINANK PATEL |
| Applicant returned to address corrections | 2/11/2022 | PINANK PATEL |
| Plan Check Approved | 3/25/2022 | PINANK PATEL |
| Issued | 3/25/2022 | APPLICANT |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| CofO in Progress | 3/31/2023 | RYAN SALAZAR |
| Permit Finaled | 4/17/2023 | MICHAEL SMITH |
| CofO Issued | 4/17/2023 | MICHAEL SMITH |
| Permit Finaled | 4/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/4/2022 | WALTER RAMIREZ |
| Address approval | Cleared | 1/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/1/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/17/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/4/2022 | Conditional Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/5/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/5/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 4/5/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 4/5/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 4/5/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 4/8/2022 | Approved | RICHARD DOCKUS |
| Sewer | 4/20/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 5/6/2022 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Partial Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 5/11/2022 | Partial Approval | ALAN MORELOS |
| Underground Mechanical | 5/11/2022 | Partial Approval | ALAN MORELOS |
| BUILDING-Rough-Frame | 5/27/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/27/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 5/27/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 5/27/2022 | No Access for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 5/27/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 6/2/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 6/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 6/2/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/4/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/4/2022 | Off-Hour Fees Due | |
| HVAC-Rough | 6/4/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 6/4/2022 | Off-Hour Fees Due | |
| PLUMBING-Rough | 6/4/2022 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 6/9/2022 | Approved | RICHARD DOCKUS |
| Insulation | 6/23/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 7/2/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 7/2/2022 | Not Ready for Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 8/25/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/13/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 10/13/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/31/2022 | Approved | RICHARD DOCKUS |
| Final | 10/31/2022 | Corrections Issued | RICHARD DOCKUS |
| Gas Test | 10/31/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 10/31/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 10/31/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | RICHARD DOCKUS |
| Service/Power Release | 10/31/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 11/21/2022 | Not Ready for Inspection | ROBERT GOLD |
| Final | 3/22/2023 | Partial Inspection | RYAN SALAZAR |
| Final | 3/30/2023 | OK to Issue CofO | RYAN SALAZAR |