15351 W ERWIN ST 91411

Certificate Information: 15351 W ERWIN ST 91411

Application / Permit
21014-20000-05578
Plan Check / Job No.
B21VN15254
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
34'4" X 14' 8" ADDITION AND CONVERSION OF (E) GARAGE TO ADU. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 3/25/2022
Issuing Office
Current Status
CofO Issued on 4/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/17/2021 PINANK PATEL
Corrections Issued 11/19/2021 PINANK PATEL
Applicant returned to address corrections 2/11/2022 PINANK PATEL
Plan Check Approved 3/25/2022 PINANK PATEL
Issued 3/25/2022 APPLICANT
Building Plans Picked Up 3/25/2022 APPLICANT
CofO in Progress 3/31/2023 RYAN SALAZAR
Permit Finaled 4/17/2023 MICHAEL SMITH
CofO Issued 4/17/2023 MICHAEL SMITH
Permit Finaled 4/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 1/4/2022 WALTER RAMIREZ
Address approval Cleared 1/19/2022 CARLOS AGUILERA
Sewer availability Cleared 2/1/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/22/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/17/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/4/2022 Conditional Approval RICHARD DOCKUS
BUILDING-Rough-Frame 4/5/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 4/5/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 4/5/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 4/5/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 4/5/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 4/8/2022 Approved RICHARD DOCKUS
Sewer 4/20/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 5/6/2022 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Partial Approval ALAN MORELOS
Interior/Exterior Lathing 5/11/2022 Partial Approval ALAN MORELOS
Underground Mechanical 5/11/2022 Partial Approval ALAN MORELOS
BUILDING-Rough-Frame 5/27/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 5/27/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 5/27/2022 Approved RICHARD DOCKUS
HVAC-Rough 5/27/2022 No Access for Inspection RICHARD DOCKUS
PLUMBING-Rough 5/27/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 6/2/2022 Corrections Issued RICHARD DOCKUS
HVAC-Rough 6/2/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 6/2/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/4/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 6/4/2022 Approved GREGG CUMMINGS
ELECTRICAL-Rough 6/4/2022 Off-Hour Fees Due
HVAC-Rough 6/4/2022 Corrections Issued GREGG CUMMINGS
HVAC-Rough 6/4/2022 Off-Hour Fees Due
PLUMBING-Rough 6/4/2022 Off-Hour Fees Due
BUILDING-Rough-Frame 6/9/2022 Approved RICHARD DOCKUS
HVAC-Rough 6/9/2022 Approved RICHARD DOCKUS
Insulation 6/23/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 7/2/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 7/2/2022 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 8/25/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/13/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Not Ready RICHARD DOCKUS
Smoke Detectors 10/13/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 10/31/2022 Approved RICHARD DOCKUS
Final 10/31/2022 Corrections Issued RICHARD DOCKUS
Gas Test 10/31/2022 Approved RICHARD DOCKUS
Green Building Final 10/31/2022 Approved RICHARD DOCKUS
HVAC-Final 10/31/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved RICHARD DOCKUS
Service/Power Release 10/31/2022 Corrections Issued RICHARD DOCKUS
Final 11/21/2022 Not Ready for Inspection ROBERT GOLD
Final 3/22/2023 Partial Inspection RYAN SALAZAR
Final 3/30/2023 OK to Issue CofO RYAN SALAZAR