11526 N BAIRD AVE 91326

Certificate Information: 11526 N BAIRD AVE 91326

Application / Permit
21014-20000-05577
Plan Check / Job No.
B21VN15250
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
212 SQ. FT. ADDITION AT THE 2ND FLOOR TO THE EXISTING 2-STORY SINGLE FAMILY DWELLING AND REMODEL THE EXISTING 130 SQ. FT. BATHROOM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 COLIN LOREDO
Corrections Issued 12/9/2021 COLIN LOREDO
Quality Review Completed 12/22/2021 OMID HEDAYAT
Building Plans Picked Up 1/7/2022 APPLICANT
Plan Check Approved 4/21/2022 COLIN LOREDO
Issued 4/11/2024 APPLICANT
CofO in Progress 5/22/2025 STEVEN BACK
Permit Finaled 5/22/2025 JOHN JANSON
CofO Issued 5/22/2025 JOHN JANSON
Permit Finaled 5/22/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/15/2022 CARLOS AGUILERA
Sewer availability Cleared 3/15/2022 CARLOS AGUILERA
Watercourse Cleared 3/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/16/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/16/2022 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Kardjian,, Vahe Matios; Lic. No.: C40821 1112 W BURBANK BLVD STE 301      BURBANK, CA 91506

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2024 Partial Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 4/26/2024 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 4/26/2024 Corrections Issued STEVEN BACK
Deputy Drilled-In Anchors 4/29/2024 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval STEVEN BACK
Footing/Foundation/Slab 5/1/2024 Approved STEVEN BACK
ELECTRICAL-Rough 6/11/2024 Approved STEVEN BACK
PLUMBING-Rough 6/11/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 7/1/2024 Approved STEVEN BACK
Green Building Rough 7/1/2024 Approved STEVEN BACK
Insulation 7/10/2024 Approved STEVEN BACK
Interior/Exterior Lathing 7/10/2024 Not Ready for Inspection STEVEN BACK
Drywall Nailing 7/19/2024 Approved STEVEN BACK
Interior/Exterior Lathing 8/6/2024 Not Ready for Inspection STEVEN BACK
Shower Pan 8/6/2024 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 8/8/2024 Partial Approval STEVEN BACK
Shower Pan 8/8/2024 Not Ready for Inspection STEVEN BACK
Shower Pan 8/20/2024 Approved SCOTT SOBEL
Interior/Exterior Lathing 9/3/2024 Not Ready for Inspection SCOTT SOBEL
Interior/Exterior Lathing 9/11/2024 Partial Approval GEVORK IPCHYAN
Final 5/21/2025 OK to Issue CofO STEVEN BACK
Green Building Final 5/21/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved STEVEN BACK
Smoke Detectors 5/21/2025 Approved STEVEN BACK