20446 W LANARK ST 91306

Certificate Information: 20446 W LANARK ST 91306

Application / Permit
21014-20000-05568
Plan Check / Job No.
B21VN15219
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERSION OF AN EXISTING 329 SF GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 1/4/2023
Issuing Office
Current Status
CofO Issued on 6/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 MICHAEL LOPEZ
Corrections Issued 11/5/2021 MICHAEL LOPEZ
Plan Check Approved 2/25/2022 MICHAEL LOPEZ
Issued 1/4/2023 APPLICANT
CofO in Progress 6/9/2023 ALEXANDER HANDY
CofO in Progress 6/9/2023 ALEXANDER HANDY
Permit Finaled 6/26/2023 JOHN JANSON
CofO Issued 6/26/2023 JOHN JANSON
Permit Finaled 6/26/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/8/2021 CARLOS AGUILERA
Sewer availability Cleared 11/8/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/9/2021 CARLOS AGUILERA

Contact Information

Contractor Fejes Zoltan; Lic. No.: 1089351-B       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/22/2023 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 3/8/2023 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 4/12/2023 Partial Approval ALEXANDER HANDY
ELECTRICAL-Rough 4/12/2023 Corrections Issued ALEXANDER HANDY
Green Building Rough 4/12/2023 Approved ALEXANDER HANDY
HVAC-Rough 4/12/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 4/12/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 4/25/2023 Approved ALEXANDER HANDY
Drywall Nailing 4/25/2023 Approved ALEXANDER HANDY
Green Building Rough 4/25/2023 Approved ALEXANDER HANDY
Insulation 4/25/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 4/25/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 5/25/2023 Not Ready for Inspection JOHN KIDWELL
Final 5/30/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 5/30/2023 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Not Required ALEXANDER HANDY
Smoke Detectors 5/30/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 6/5/2023 Approved ALEXANDER HANDY
Final 6/5/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 6/5/2023 Not Ready for Inspection ALEXANDER HANDY
Service/Power Release 6/5/2023 Approved ALEXANDER HANDY
Final 6/8/2023 OK to Issue CofO ALEXANDER HANDY
Green Building Final 6/8/2023 Approved ALEXANDER HANDY
HVAC-Final 6/8/2023 Approved ALEXANDER HANDY
PLUMBING-Final 6/8/2023 Approved ALEXANDER HANDY