20446 W LANARK ST 91306
Certificate Information: 20446 W LANARK ST 91306
- Application / Permit
- 21014-20000-05568
- Plan Check / Job No.
- B21VN15219
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERSION OF AN EXISTING 329 SF GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 1/4/2023
- Issuing Office
- Current Status
- CofO Issued on 6/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | MICHAEL LOPEZ |
| Corrections Issued | 11/5/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 2/25/2022 | MICHAEL LOPEZ |
| Issued | 1/4/2023 | APPLICANT |
| CofO in Progress | 6/9/2023 | ALEXANDER HANDY |
| CofO in Progress | 6/9/2023 | ALEXANDER HANDY |
| Permit Finaled | 6/26/2023 | JOHN JANSON |
| CofO Issued | 6/26/2023 | JOHN JANSON |
| Permit Finaled | 6/26/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/8/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/8/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Fejes Zoltan; Lic. No.: 1089351-B | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/22/2023 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 3/8/2023 | Conditional Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/12/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/12/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 4/12/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 4/12/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 4/12/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/25/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 4/25/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 4/25/2023 | Approved | ALEXANDER HANDY |
| Insulation | 4/25/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 4/25/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 5/25/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 5/30/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/30/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Not Required | ALEXANDER HANDY |
| Smoke Detectors | 5/30/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 6/5/2023 | Approved | ALEXANDER HANDY |
| Final | 6/5/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 6/5/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 6/5/2023 | Approved | ALEXANDER HANDY |
| Final | 6/8/2023 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 6/8/2023 | Approved | ALEXANDER HANDY |
| HVAC-Final | 6/8/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 6/8/2023 | Approved | ALEXANDER HANDY |