15128-15130 W MARSON ST 91402
Certificate Information: 15128-15130 W MARSON ST 91402
- Application / Permit
- 21014-20000-05558
- Plan Check / Job No.
- B21VN15203
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20' x 10' GARAGE AND ADD 12'10" x 10' FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). ADD 4'2" x 5'5" FOR MAIN DWELLING. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2021 | JEFFREY TANGONAN |
| Corrections Issued | 11/16/2021 | JEFFREY TANGONAN |
| Issued | 12/2/2021 | APPLICANT |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| CofO in Progress | 3/14/2022 | GREGG CUMMINGS |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2021 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 11/18/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 11/19/2021 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/8/2021 | Partial Approval | GREGG CUMMINGS |
| Sewer | 12/8/2021 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 12/9/2021 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/16/2021 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 1/4/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/4/2022 | Approved | GREGG CUMMINGS |
| Gas Test | 1/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 1/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/4/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/10/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 1/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 1/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/18/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 1/18/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 1/18/2022 | Approved | GREGG CUMMINGS |
| Insulation | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 1/24/2022 | Approved | GREGG CUMMINGS |
| Insulation | 1/24/2022 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 1/26/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/26/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 1/31/2022 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 1/31/2022 | Approved | WILLIAM WREN |
| Shower Pan | 1/31/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 2/2/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 2/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/28/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/28/2022 | Approved | GREGG CUMMINGS |
| HVAC-Final | 2/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 2/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 2/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/14/2022 | Approved | GREGG CUMMINGS |
| Final | 3/14/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 3/14/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 3/14/2022 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 3/14/2022 | Approved | GREGG CUMMINGS |