3556 N LOWRY ROAD 90027
Certificate Information: 3556 N LOWRY ROAD 90027
- Application / Permit
- 21014-20000-05550
- Plan Check / Job No.
- B21VN15188
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING TO CONVERT PORTION OF (E) 27'-11" x 13'-8" IRREGULAR SHAPED CRAWL SPACE INTO A NEW PLAYROOOM, REINFORCE FOUNDATION AND REPAIR / REPLACE PORTION OF (E)RET. WALL . SEE COMMENTS.
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/11/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 11/17/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 11/23/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Plan Check Approved | 4/5/2023 | SARKIS HARABEDIAN |
| Issued | 5/24/2023 | APPLICANT |
| CofO in Progress | 11/5/2024 | ENRIQUE MIRELES |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
| CofO Issued | 11/10/2024 | DEROLD HAUFF |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/18/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/18/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/18/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/18/2022 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/18/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | CELINA MORENO |
| Sewer availability | Cleared | 4/18/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 5/7/2022 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 4/5/2023 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Aparicio,, Daniel Gonzalo; Lic. No.: C92121 | 19332 AVENIDA DEL SOL WALNUT, CA 91789 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Geologist | Carrle,, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/14/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 6/16/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 7/11/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 7/14/2023 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/18/2023 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/21/2023 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 8/31/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/27/2023 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 1/2/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 1/19/2024 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/23/2024 | Approved | LILIANA PORTILLO |
| Wood Frame | 3/6/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 4/22/2024 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/22/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Pre-Inspection | 4/30/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 5/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 5/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 5/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 5/10/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/10/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/10/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/10/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/10/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 5/28/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/28/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 6/5/2024 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/30/2024 | Partial Approval | BRENDAN MORELLI |
| Pre-Inspection | 7/30/2024 | Partial Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/23/2024 | Approved | ENRIQUE MIRELES |
| Final | 9/20/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/20/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/20/2024 | Approved | ENRIQUE MIRELES |
| Final | 9/25/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 10/7/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 10/9/2024 | OK to Issue CofO | ENRIQUE MIRELES |