5604 N LE SAGE AVE 91367

Certificate Information: 5604 N LE SAGE AVE 91367

Application / Permit
21014-20000-05549
Plan Check / Job No.
B21VN15187
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
16'-6" X 28'-6" ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/15/2022
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 JEROME MAGAT PALMA
Corrections Issued 11/14/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 2/14/2022 JEROME MAGAT PALMA
Plan Check Approved 2/15/2022 JEROME MAGAT PALMA
Issued 2/15/2022 APPLICANT
Building Plans Picked Up 2/22/2022 APPLICANT
CofO in Progress 8/11/2022 TROY SANDERS
CofO Issued 9/10/2022 DANIEL ORRANTE
Permit Finaled 9/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/22/2021 AMIR KASHFI
Roof/Waste drainage to street Cleared 11/22/2021 AMIR KASHFI
Grading Pre-Inspection Cleared 12/8/2021 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 1/3/2022 AMIR KASHFI
Sewer availability Cleared 1/3/2022 AMIR KASHFI
Low Impact Development Cleared 1/20/2022 MARCO SANCHEZ
Construction near power lines Cleared 2/15/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John Marshall; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/22/2022 Partial Approval TROY SANDERS
Pre-Inspection 2/22/2022 Approved TROY SANDERS
Sewer 2/22/2022 Approved TROY SANDERS
Underground Mechanical 2/22/2022 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 3/15/2022 Approved TROY SANDERS
Footing/Foundation/Slab 3/15/2022 Approved TROY SANDERS
Special/Order Compliance 3/15/2022 Corrections Issued TROY SANDERS
BUILDING-Rough-Frame 6/7/2022 Not Ready for Inspection TROY SANDERS
Green Building Rough 6/7/2022 Not Ready for Inspection TROY SANDERS
Rough-Elec/Plmb/HVAC 6/7/2022 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 6/9/2022 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 6/9/2022 Approved TROY SANDERS
Insulation 6/16/2022 Conditional Approval JESUS PINEDA
Interior/Exterior Lathing 6/16/2022 Partial Approval JESUS PINEDA
Drywall Nailing 6/27/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/27/2022 Approved MORRIS JACKSON
Shower Pan 6/27/2022 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/3/2022 Approved TROY SANDERS
Final 8/3/2022 Corrections Issued TROY SANDERS
Green Building Final 8/3/2022 Approved TROY SANDERS
Green Building Rough 8/3/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 8/3/2022 Approved TROY SANDERS
Final 8/11/2022 OK to Issue CofO TROY SANDERS
Service/Power Release 8/11/2022 Approved TROY SANDERS