5604 N LE SAGE AVE 91367
Certificate Information: 5604 N LE SAGE AVE 91367
- Application / Permit
- 21014-20000-05549
- Plan Check / Job No.
- B21VN15187
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 16'-6" X 28'-6" ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 11/14/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 2/14/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/15/2022 | JEROME MAGAT PALMA |
| Issued | 2/15/2022 | APPLICANT |
| Building Plans Picked Up | 2/22/2022 | APPLICANT |
| CofO in Progress | 8/11/2022 | TROY SANDERS |
| CofO Issued | 9/10/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/10/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2021 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 11/22/2021 | AMIR KASHFI |
| Grading Pre-Inspection | Cleared | 12/8/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/3/2022 | AMIR KASHFI |
| Low Impact Development | Cleared | 1/20/2022 | MARCO SANCHEZ |
| Construction near power lines | Cleared | 2/15/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John Marshall; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/22/2022 | Partial Approval | TROY SANDERS |
| Pre-Inspection | 2/22/2022 | Approved | TROY SANDERS |
| Sewer | 2/22/2022 | Approved | TROY SANDERS |
| Underground Mechanical | 2/22/2022 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 3/15/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 3/15/2022 | Approved | TROY SANDERS |
| Special/Order Compliance | 3/15/2022 | Corrections Issued | TROY SANDERS |
| BUILDING-Rough-Frame | 6/7/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 6/7/2022 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 6/9/2022 | Approved | TROY SANDERS |
| Insulation | 6/16/2022 | Conditional Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 6/16/2022 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 6/27/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/27/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 6/27/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | TROY SANDERS |
| Final | 8/3/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 8/3/2022 | Approved | TROY SANDERS |
| Green Building Rough | 8/3/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/3/2022 | Approved | TROY SANDERS |
| Final | 8/11/2022 | OK to Issue CofO | TROY SANDERS |
| Service/Power Release | 8/11/2022 | Approved | TROY SANDERS |