4337 N RHODES AVE 91604

Certificate Information: 4337 N RHODES AVE 91604

Application / Permit
21014-20000-05548
Plan Check / Job No.
B21VN15185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'3" x 26'3" (IRR SHAPE) ADDITION TO ADD BEDROOM AND ENLARGE KITCHEN. INTERIOR REMODEL TO THE (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 12/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/17/2021 JEFFREY TANGONAN
Corrections Issued 11/18/2021 JEFFREY TANGONAN
Plan Check Approved 2/7/2022 JEFFREY TANGONAN
Issued 3/23/2022 APPLICANT
Building Plans Picked Up 4/18/2022 APPLICANT
CofO in Progress 7/10/2023 JACK KARGODORIAN
CofO Issued 12/2/2024 DANIEL ORRANTE
Permit Finaled 12/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/21/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/21/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/28/2022 DAGOVERTO GUERRERO

Contact Information

Architect Brouse,, Jon Robert; Lic. No.: C22200 12930 VENTURA BLVD SUITE 214      STUDIO CITY, CA 91604
Contractor P F I Construction Inc; Lic. No.: 1032307-B 4717 ROCKLAND PLACE      LA CANADA, CA 91011

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/21/2022 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 4/21/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 4/28/2022 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 5/12/2022 Conditional Approval ARAM AVEDISIAN
Insulation 5/16/2022 Partial Approval ARAM AVEDISIAN
Wood Frame 5/16/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/18/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 7/18/2022 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 7/18/2022 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 7/18/2022 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/25/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 7/25/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/25/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/15/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/15/2022 Approved CHRISTOPHE COCHRAN
Insulation 8/19/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/19/2022 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 8/31/2022 Approved CHRISTOPHE COCHRAN
Shower Pan 9/6/2022 Approved CHRISTOPHE COCHRAN
Service/Power Release 11/15/2022 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 11/28/2022 Corrections Issued CHRISTOPHE COCHRAN
Final 3/22/2023 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 3/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 5/22/2023 Partial Inspection JOHN COLEMAN
Final 5/22/2023 Not Ready for Inspection JOHN COLEMAN
Green Building Final 5/22/2023 Corrections Issued JOHN COLEMAN
HVAC-Final 5/22/2023 Approved JOHN COLEMAN
PLUMBING-Final 5/22/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Approved JOHN COLEMAN
Smoke Detectors 5/22/2023 Approved JOHN COLEMAN
Final 5/26/2023 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 5/26/2023 Approved CHRISTOPHE COCHRAN
Final 7/7/2023 OK to Issue CofO JACK KARGODORIAN