5188 N GAYNOR AVE 91436
Certificate Information: 5188 N GAYNOR AVE 91436
- Application / Permit
- 21014-20000-05540
- Plan Check / Job No.
- B21VN15155
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 21'-0" x 24'-0" IRREGULAR SHAPED ADDITION TO THE (E)SINGLE FAMILY DWELLING FOR A NEW BEDROOM,BATHROOM, CLOSET AND LAUNDRY ROOM AND REMODEL KITCHEN. WORK DONE PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 07/26/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 9/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 11/22/2021 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 3/2/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 3/16/2022 | SARKIS HARABEDIAN |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| CofO in Progress | 2/26/2025 | THOMAS FINNILA |
| Permit Finaled | 9/30/2025 | MICHAEL PELHAM |
| CofO Issued | 9/30/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/30/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/6/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/8/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/21/2023 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 12/21/2023 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 12/21/2023 | Not Ready for Inspection | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/23/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/30/2024 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Corrections Issued | HENRY KIM |
| Insulation | 5/1/2024 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/7/2024 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/7/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Corrections Issued | JEFFREY BULL |
| BUILDING-Rough-Frame | 6/4/2024 | Corrections Issued | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 6/4/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 6/12/2024 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/18/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 6/18/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | MORRIS JACKSON |
| MERV13>=Rough | 6/18/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 6/18/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Insulation | 6/21/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/26/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | THOMAS FINNILA |
| Final | 10/24/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Grading Pre-Inspection | 10/24/2024 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 10/24/2024 | Approved | THOMAS FINNILA |
| Smoke Detectors | 10/24/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 11/12/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 11/12/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 11/12/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 12/11/2024 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Final | 12/11/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 12/11/2024 | Approved | THOMAS FINNILA |
| Final | 1/16/2025 | Partial Approval | THOMAS FINNILA |
| Final | 2/25/2025 | OK to Issue CofO | THOMAS FINNILA |