13106 W MERCER ST 91331
Certificate Information: 13106 W MERCER ST 91331
- Application / Permit
- 21014-20000-05532
- Plan Check / Job No.
- B21VN15133
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 19'-6" X 35'-0" BEDROOM/BATHROOM AND RECREATION ROOM W/ WET BAR AND EXTERIOR ACCESS ONLY TO AN (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | JENNIFER LEE |
| Corrections Issued | 12/6/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 3/23/2022 | JENNIFER LEE |
| Applicant returned to address corrections | 4/11/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/11/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Plan Check Approved | 4/20/2022 | JON BLAINE |
| Issued | 4/22/2022 | APPLICANT |
| CofO in Progress | 7/7/2022 | MICHEL ABAJAN |
| CofO Issued | 7/14/2022 | RONALD MYRICK |
| Permit Finaled | 7/14/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 11/24/2021 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 3/9/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/18/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 5/17/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 5/17/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/23/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/23/2022 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/23/2022 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Final | 5/23/2022 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 5/23/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/23/2022 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/27/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/27/2022 | Approved | MICHEL ABAJAN |
| Insulation | 6/1/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/1/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/2/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/7/2022 | Approved | MICHEL ABAJAN |
| Final | 7/7/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 7/7/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/7/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/7/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Approved | MICHEL ABAJAN |