2422 E RIVERDALE AVE 90031

Certificate Information: 2422 E RIVERDALE AVE 90031

Application / Permit
21014-20000-05531
Plan Check / Job No.
B21VN15124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'4" X 24'11" ADDITION TO AND CONVERT 22'7" X 23'9" SFD TO ACCESSORY DWELLING UNIT AS PER LAMC12.22.A.33(C) AND (D), ADDITION TO ENLARGE BEDROOM , LIVING ROOM , BATHROOM AND REMODEL BEDROOM , BATHROOM , LIVING ROOM AND KITCHEN , RE-FRAME THE ROOF, NEW ROOFTOP A/C UNIT, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 RARES BODEA
Corrections Issued 12/10/2021 RARES BODEA
Quality Review Completed 12/16/2021 STEVEN KIM
Building Plans Picked Up 12/21/2021 APPLICANT
Applicant returned to address corrections 3/4/2022 RARES BODEA
Applicant returned to address corrections 6/1/2022 RARES BODEA
Plan Check Approved 6/2/2022 RARES BODEA
Issued 6/7/2022 APPLICANT
CofO in Progress 3/15/2023 THOMAS LOGRASSO
Permit Finaled 3/23/2023 DEROLD HAUFF
Permit Finaled 3/23/2023 DEROLD HAUFF
CofO Issued 3/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/29/2022 WALLIE JONG
Sewer availability Cleared 3/29/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/30/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/30/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 4/4/2022 AMAAN MALIK
Tenant Habitability Plan Cleared 4/5/2022 MICHAEL SOTO
Roof/Waste drainage to street Cleared 4/7/2022 JEANETTE VONG
Construction near power lines Cleared 4/22/2022 WALTER RAMIREZ
ZI Cleared 5/5/2022 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 121 N VAIL AVE      MONTEBELLO, CA 90640

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/11/2022 Partial Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 7/14/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval RUBEN SALAS
PLUMBING-Rough 8/23/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 8/26/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/26/2022 Not Ready for Inspection THOMAS LOGRASSO
Sewer 8/26/2022 Approved THOMAS LOGRASSO
Underground Mechanical 8/26/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 9/9/2022 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 9/9/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 9/9/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 9/9/2022 Not Ready for Inspection THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 9/9/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 9/22/2022 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 9/22/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/29/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 9/29/2022 Approved THOMAS LOGRASSO
Green Building Rough 9/29/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 9/29/2022 Approved THOMAS LOGRASSO
Insulation 10/3/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 10/13/2022 Approved THOMAS LOGRASSO
Drywall Nailing 10/13/2022 Approved THOMAS LOGRASSO
Green Building Rough 10/13/2022 Approved THOMAS LOGRASSO
Insulation 10/13/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/13/2022 Approved THOMAS LOGRASSO
Shower Pan 10/13/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/20/2022 Approved THOMAS LOGRASSO
Green Building Rough 10/20/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/20/2022 Approved THOMAS LOGRASSO
Drywall Nailing 2/22/2023 Approved STUART CHAPMAN
Final 2/22/2023 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 2/22/2023 Approved STUART CHAPMAN
Green Building Final 2/22/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 2/22/2023 Approved STUART CHAPMAN
Final 3/8/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved THOMAS LOGRASSO
Final 3/14/2023 OK to Issue CofO THOMAS LOGRASSO