5677 E BUCHANAN ST 90042
Certificate Information: 5677 E BUCHANAN ST 90042
- Application / Permit
- 21014-20000-05524
- Plan Check / Job No.
- B21VN15106
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND FLOOR ADDITION TO THE (E) SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Valley
- Current Status
- Issued on 2/21/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | COLIN LOREDO |
| Corrections Issued | 12/6/2021 | COLIN LOREDO |
| Quality Review Completed | 12/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/15/2021 | APPLICANT |
| Applicant returned to address corrections | 6/9/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 1/12/2023 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 1/26/2023 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 2/7/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 2/9/2023 | MARVEL DELACRUZ |
| Issued | 2/21/2023 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/29/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/23/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 5/23/2022 | ABEL CASILLAS |
| Grading Pre-Inspection | Cleared | 6/8/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2022 | ABEL CASILLAS |
| HPOZ | Cleared | 12/19/2022 | LYDIA CHAPMAN |
| Tenant Habitability Plan | Cleared | 1/12/2023 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 2/6/2023 | TREVOR QUAN |
| GPI Written Notices | Cleared | 2/9/2023 | MARVEL DELACRUZ |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/7/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/14/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 9/14/2023 | Approved | ROY SPAULDING |
| HVAC-Rough | 9/14/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/14/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 9/21/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 9/21/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 10/10/2023 | Approved | ROY SPAULDING |
| Pre-Inspection | 11/18/2024 | Corrections Issued | ALIZAH MAYAGOITIA |