16001 W LEADWELL ST 91406
Certificate Information: 16001 W LEADWELL ST 91406
- Application / Permit
- 21014-20000-05493
- Plan Check / Job No.
- B21VN15019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (9'-4"x25'-2"), 249 SQ. FT. ADDITION TO THE (E) SFD W/INTERIOR REMODEL, PER ENG.
- Permit Issued
- Issued on 3/7/2022
- Issuing Office
- Current Status
- CofO Issued on 12/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | PETER MOSESIAN |
| Corrections Issued | 11/9/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Issued | 3/7/2022 | APPLICANT |
| CofO in Progress | 12/23/2022 | RAUL OLAGI |
| CofO Issued | 12/28/2022 | MICHAEL SMITH |
| Permit Finaled | 12/28/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/17/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 2/18/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/1/2022 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 6/1/2022 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 6/8/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 6/24/2022 | Partial Approval | ALAN MORELOS |
| Special/Order Compliance | 6/24/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Rough | 8/11/2022 | Not Ready for Inspection | ALAN MORELOS |
| PLUMBING-Rough | 8/11/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/16/2022 | Not Ready for Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 9/16/2022 | Corrections Issued | ALAN MORELOS |
| HVAC-Rough | 9/16/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 9/16/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Rough | 9/21/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/21/2022 | Partial Approval | ALAN MORELOS |
| Insulation | 9/22/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/26/2022 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 9/26/2022 | Conditional Approval | RAUL OLAGI |
| Green Building Rough | 9/26/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/26/2022 | Approved | RAUL OLAGI |
| Shower Pan | 9/26/2022 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 9/29/2022 | Approved | RAUL OLAGI |
| Special/Order Compliance | 9/29/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 12/1/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/1/2022 | Corrections Issued | RAUL OLAGI |
| Final | 12/1/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 12/1/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 12/1/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 12/1/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 12/1/2022 | Approved | RAUL OLAGI |
| Final | 12/23/2022 | OK to Issue CofO | RAUL OLAGI |