6526 N GENTRY AVE 91606
Certificate Information: 6526 N GENTRY AVE 91606
- Application / Permit
- 21014-20000-05492
- Plan Check / Job No.
- B21VN15018
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED RECROOM WITH AN ADDITION TO AN ATTACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2021 | CARLOS MONTES |
| Corrections Issued | 11/8/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/7/2021 | CARLOS MONTES |
| Plan Check Approved | 12/20/2021 | CARLOS MONTES |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 6/30/2023 | JOHN HAYES |
| Permit Finaled | 7/19/2023 | MICHAEL SMITH |
| CofO Issued | 7/19/2023 | MICHAEL SMITH |
| Permit Finaled | 7/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 11/23/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/16/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 7/13/2022 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 7/22/2022 | Conditional Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/3/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 10/3/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 10/3/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/3/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 11/7/2022 | Approved | JOHN HAYES |
| Gas Test | 11/7/2022 | Approved | JOHN HAYES |
| Green Building Rough | 11/7/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 11/7/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 11/7/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 12/5/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 12/5/2022 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 12/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 1/4/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/7/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 6/7/2023 | Approved | JOHN HAYES |
| Green Building Final | 6/7/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 6/7/2023 | Approved | JOHN HAYES |
| Final | 6/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 6/21/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 6/29/2023 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | JOHN HAYES |