3972 S CLOVERDALE AVE 90008

Certificate Information: 3972 S CLOVERDALE AVE 90008

Application / Permit
21014-20000-05474
Plan Check / Job No.
B21VN14968
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(9'-0"x6'-0"), 54 SQFT 2ND FLOOR ADDITION & REMODEL TO (E) SFD
Permit Issued
Issued on 10/3/2022
Issuing Office
Current Status
Issued on 10/3/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 MARVEL DELACRUZ
Corrections Issued 11/14/2021 MARVEL DELACRUZ
Quality Review Completed 11/23/2021 STEVEN KIM
Building Plans Picked Up 11/23/2021 APPLICANT
Plan Check Approved 10/3/2022 PETER MOSESIAN
Issued 10/3/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/20/2022 JEANETTE VONG
Sewer availability Cleared 5/20/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/25/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/16/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 8/16/2024 Not Ready for Inspection ANTHONY EGSON
METHANE-Rough 8/16/2024 Not Ready for Inspection ANTHONY EGSON
Rough-Elec/Plmb/HVAC 8/16/2024 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 8/27/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 8/27/2024 Approved ANTHONY EGSON
METHANE-Rough 8/27/2024 Not Ready for Inspection ANTHONY EGSON
Rough-Elec/Plmb/HVAC 8/27/2024 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 9/5/2024 Not Ready for Inspection ANTHONY EGSON
Rough-Elec/Plmb/HVAC 9/5/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 9/10/2024 Partial Approval ANTHONY EGSON
METHANE-Rough 9/10/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Approved ANTHONY EGSON
Insulation 9/17/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/17/2024 Approved ANTHONY EGSON
Drywall Nailing 9/20/2024 Approved ALEX COLIN
BUILDING-Rough-Frame 11/25/2024 Not Ready for Inspection BARRY HACHE
Final 11/25/2024 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 11/25/2024 Not Ready for Inspection BARRY HACHE
Green Building Final 11/25/2024 Not Ready for Inspection BARRY HACHE
METHANE-Barrier 11/25/2024 Not Ready for Inspection BARRY HACHE
METHANE-Final 11/25/2024 Not Ready for Inspection BARRY HACHE
METHANE-Rough 11/25/2024 Not Ready for Inspection BARRY HACHE
METHANE-Subgrade 11/25/2024 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready BARRY HACHE
Smoke Detectors 11/25/2024 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 12/5/2024 Approved ENRIQUE MIRELES
Final 12/5/2024 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 12/5/2024 Approved ENRIQUE MIRELES
Green Building Final 12/5/2024 Approved ENRIQUE MIRELES
METHANE-Barrier 12/5/2024 Approved ENRIQUE MIRELES
METHANE-Final 12/5/2024 Approved ENRIQUE MIRELES
METHANE-Rough 12/5/2024 Approved ENRIQUE MIRELES
METHANE-Subgrade 12/5/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/5/2024 SGSOV Not Ready ENRIQUE MIRELES
Final 12/17/2024 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/17/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/17/2024 Approved ENRIQUE MIRELES