14430 W JUDD ST 91331
Certificate Information: 14430 W JUDD ST 91331
- Application / Permit
- 21014-20000-05468
- Plan Check / Job No.
- B21VN14931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 20' (E) DETACHED GARAGE AND ADD 16' X 24' IRREGULAR SHAPED INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/27/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/7/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/1/2021 | RAPHAEL ROSAS |
| Issued | 12/27/2021 | APPLICANT |
| Building Plans Picked Up | 12/30/2021 | APPLICANT |
| CofO in Progress | 3/31/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 4/13/2022 | RONALD MYRICK |
| CofO Issued | 4/13/2022 | RONALD MYRICK |
| Permit Finaled | 4/13/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2021 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 11/10/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 11/12/2021 | AMIR KASHFI |
Contact Information
| Contractor | Golden Construction Group Llc; Lic. No.: 1078364-B | 16814 CITRONIA STREET NORTHRIDGE, CA 91343 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Barrier | 1/24/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 1/24/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 1/25/2022 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 1/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 2/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 2/7/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/10/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 2/10/2022 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 2/10/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 2/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 2/16/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/16/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/18/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/18/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/18/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/23/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/25/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 3/25/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/25/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 3/25/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/30/2022 | Approved | JENNIFER RABUCHIN |
| Final | 3/30/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Gas Test | 3/30/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/30/2022 | Approved | JENNIFER RABUCHIN |