ePlan SFD addition 605 SF. Room addition to Existing Dwelling.Add 2-bedrooms, 2-Bathrooms,CLosets Remodel Kitchen, Interior Alterations, Remodel Existing Bathrooms.
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 ARSALAN SHABESTARI
Corrections Issued 11/27/2021 ARSALAN SHABESTARI
Quality Review Completed 12/2/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/20/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 2/11/2022 ARSALAN SHABESTARI
Plan Check Approved 2/23/2022 ARSALAN SHABESTARI
Issued 3/1/2022 APPLICANT
CofO in Progress 8/4/2022 ARAM AVEDISIAN
No Progress 8/22/2022 ROBERT GOLD
CofO in Progress 8/29/2022 ARAM AVEDISIAN
No Progress 8/29/2022 ARAM AVEDISIAN
CofO in Progress 8/29/2022 ARAM AVEDISIAN
CofO Issued 8/30/2022 MICHAEL SMITH
Permit Finaled 8/30/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 12/7/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/8/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 12/20/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/23/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 2/17/2022 BRIAN MILLER
GPI Written Notices Cleared 2/23/2022 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: NA43590       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/16/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/22/2022 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 3/24/2022 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 3/24/2022 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/29/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/1/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 4/19/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 4/19/2022 Partial Approval JOHN HAYES
Special/Order Compliance 4/19/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Partial Approval JOHN HAYES
Deputy Wood Construction 5/11/2022 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 5/13/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 5/13/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/13/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/18/2022 Corrections Issued JOHN HAYES
Green Building Rough 5/18/2022 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 5/18/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/24/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 5/24/2022 Not Ready for Inspection MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 5/24/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/27/2022 Approved JOHN HAYES
Green Building Rough 5/27/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 5/27/2022 Approved JOHN HAYES
Insulation 6/3/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/3/2022 Partial Approval RICHARD DOCKUS
Shower Pan 6/3/2022 Approved RICHARD DOCKUS
Drywall Nailing 6/10/2022 Approved JOHN HAYES
Interior/Exterior Lathing 6/10/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Ready WILLIAM WREN
Final 7/29/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 7/29/2022 Approved ARAM AVEDISIAN
Green Building Final 7/29/2022 Approved ARAM AVEDISIAN
HVAC-Final 7/29/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 7/29/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 8/4/2022 Approved ARAM AVEDISIAN
Final 8/4/2022 OK to Issue CofO ARAM AVEDISIAN
PLUMBING-Final 8/4/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 8/4/2022 Approved ARAM AVEDISIAN