15161 W HATTERAS ST 91411

Certificate Information: 15161 W HATTERAS ST 91411

Application / Permit
21014-20000-05447
Plan Check / Job No.
B21VN14858
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
828 SQ. FT. ADDITION TO AND CONVERT (E) 360 SQ. FT. DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). REMOVE (E) GARAGE FRAME EXCEPT 9 LINEAR FEET OF WALL. RE-FRAME, EXISTING GARAGE FOOTING TO REMAIN. ALL WORK PER ENGINEERING. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 5/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/5/2021 ROSENDO MEDINA
Corrections Issued 11/10/2021 ROSENDO MEDINA
Applicant returned to address corrections 5/5/2022 OMAR GARNICA
Plan Check Approved 5/31/2022 OMAR GARNICA
Issued 5/31/2022 APPLICANT
Building Plans Picked Up 6/16/2022 APPLICANT
CofO in Progress 5/10/2023 RYAN SALAZAR
Permit Finaled 5/10/2023 MICHAEL SMITH
CofO Issued 5/10/2023 MICHAEL SMITH
Permit Finaled 5/10/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/21/2022 DAGOVERTO GUERRERO
Permit Cleared 4/21/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/26/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 4/26/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 5/18/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/15/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 8/10/2022 Corrections Issued CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 8/15/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 8/19/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 10/12/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 10/12/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 10/21/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 10/21/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 10/21/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/21/2022 Approved CHRISTOPHE COCHRAN
Insulation 10/24/2022 Corrections Issued RICHARD DOCKUS
Drywall Nailing 10/28/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 10/28/2022 Approved WILLIAM WREN
Shower Pan 10/28/2022 Approved WILLIAM WREN
Final 4/24/2023 Corrections Issued RYAN SALAZAR
Green Building Final 4/24/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 4/24/2023 Approved RYAN SALAZAR
Pre-Inspection 5/8/2023 Approved JOHN COLEMAN
Final 5/10/2023 OK to Issue CofO RYAN SALAZAR