731 S SCHUMACHER DR 90048
Certificate Information: 731 S SCHUMACHER DR 90048
- Application / Permit
- 21014-20000-05394
- Plan Check / Job No.
- B21VN14763
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 13'-0" x 16'-8" ATTACHED OPEN TRELLIS TO (E) S.F.D. PER ENGINEERING
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 10/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | ALFRED RAMIREZ |
| Corrections Issued | 10/28/2021 | ALFRED RAMIREZ |
| Issued | 1/19/2022 | APPLICANT |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| CofO in Progress | 10/6/2023 | STUART CHAPMAN |
| CofO Issued | 10/9/2023 | DEROLD HAUFF |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 11/24/2021 | JONATHAN KAPLAN |
| ZI | Cleared | 11/24/2021 | JONATHAN KAPLAN |
Contact Information
| Contractor | Custom Carpentry; Lic. No.: 826799-B | 666 OAK HILL E ONTARIO, CA 91761 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/21/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Barrier | 1/21/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 1/21/2022 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 2/22/2022 | Partial Approval | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/22/2022 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 4/22/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/10/2023 | Approved | RICHARD DOCKUS |
| Final | 7/10/2023 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 7/10/2023 | Approved | RICHARD DOCKUS |
| Green Building Rough | 7/10/2023 | Approved | RICHARD DOCKUS |
| METHANE-Final | 7/10/2023 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 7/10/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 7/10/2023 | Approved | RICHARD DOCKUS |
| Final | 10/5/2023 | OK to Issue CofO | STUART CHAPMAN |