425 E 25TH ST 90011

Certificate Information: 425 E 25TH ST 90011

Application / Permit
21014-20000-05390
Plan Check / Job No.
B21VN14744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 23' X 13'5" IRREGULAR SHAPED ADDITION TO (E) SFD TO EXTEND THE BEDROOM, AND CLOSET AND ADD A SECOND BATHROOM , ALL WORK PER ENGINEERING. COMPLY WITH DEPARTMENT ORDER effective date 07/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 6/16/2023
Issuing Office
Metro
Current Status
CofO in Progress on 11/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/11/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 RARES BODEA
Corrections Issued 11/15/2021 RARES BODEA
Building Plans Picked Up 11/16/2021 APPLICANT
Applicant returned to address corrections 9/23/2022 JESSE ARELLANO
Plan Check Approved 10/3/2022 PINANK PATEL
Plan Check Approved 6/16/2023 PINANK PATEL
Issued 6/16/2023 APPLICANT
CofO in Progress 11/10/2025 DANIEL GUEVARA

Permit Application Clearance Information

Sewer availability Cleared 11/20/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/20/2022 THAN WIN
Tenant Habitability Plan Cleared 3/15/2022 RICARDO BOHORQUEZ
Low Impact Development Cleared 6/8/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/9/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16200 VENTURA BLVD   SUITE 227    ENCINO, CA 91436

Inspector Information

JEREMY TODD, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
MARVIN FONSECA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GUEVARA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/26/2023 Corrections Issued GORDON ZUBER
BUILDING-Rough-Frame 9/20/2023 Not Ready for Inspection GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Approved GORDON ZUBER
Green Building Rough 9/20/2023 Not Ready for Inspection GORDON ZUBER
Wood Frame 9/20/2023 Not Ready for Inspection GORDON ZUBER
ELECTRICAL-Rough 12/20/2023 Approved DANIEL GUEVARA
Footing/Foundation/Slab 12/20/2023 Approved DANIEL GUEVARA
PLUMBING-Rough 12/20/2023 Conditional Approval DANIEL GUEVARA
HVAC-Rough 1/9/2024 Approved DANIEL GUEVARA
Interior/Exterior Lathing 3/13/2024 No Access for Inspection DANIEL GONZALEZ
Wood Frame 3/13/2024 No Access for Inspection DANIEL GONZALEZ
BUILDING-Rough-Frame 3/14/2024 Corrections Issued DANIEL GONZALEZ
BUILDING-Rough-Frame 5/6/2024 Approved DANIEL GUEVARA
Green Building Rough 5/6/2024 Approved DANIEL GUEVARA
Interior/Exterior Lathing 5/6/2024 Approved DANIEL GUEVARA
Insulation 5/8/2024 Approved DANIEL GUEVARA
Drywall Nailing 5/29/2024 Approved DANIEL GUEVARA
Gas Test 9/12/2024 Corrections Issued DANIEL GUEVARA
Gas Test 9/26/2024 Approved DANIEL GUEVARA
ELECTRICAL-Final 3/24/2025 Partial Approval DANIEL GUEVARA
Service/Power Release 3/24/2025 Approved DANIEL GUEVARA
HVAC-Final 4/1/2025 Approved DANIEL GUEVARA
PLUMBING-Final 4/1/2025 Approved DANIEL GUEVARA
Service/Power Release 4/30/2025 Corrections Issued DANIEL GUEVARA
ELECTRICAL-Final 9/30/2025 Approved DANIEL GUEVARA
Final 9/30/2025 Conditional Approval DANIEL GUEVARA
Green Building Final 9/30/2025 Approved DANIEL GUEVARA
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Approved DANIEL GUEVARA
Smoke Detectors 9/30/2025 Approved DANIEL GUEVARA
Final 11/5/2025 OK to Issue CofO DANIEL GUEVARA