423-423 1/2 E 25TH ST 90011

Certificate Information: 423-423 1/2 E 25TH ST 90011

Application / Permit
21014-20000-05389
Plan Check / Job No.
B21VN14743
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A 390 SQ. FT. FOR A NEW ACCESSORY DWELLING UNIT ATTACHED TO EX. DWELLING PER LAMC 12.22 A.33(c) and (e). ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/16/2023
Issuing Office
Metro
Current Status
Issued on 6/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/11/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 JEFFREY TANGONAN
Corrections Issued 11/23/2021 JEFFREY TANGONAN
Plan Check Approved 3/24/2022 JEFFREY TANGONAN
Building Plans Picked Up 4/4/2022 APPLICANT
Issued 6/16/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/3/2021 ABEL CASILLAS
Permit Cleared 12/3/2021 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 1/24/2022 ABEL CASILLAS
Sewer availability Cleared 1/24/2022 ABEL CASILLAS
Low Impact Development Cleared 6/8/2022 SUNG JOON WON

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16200 VENTURA BLVD   SUITE 227    ENCINO, CA 91436

Inspector Information

JEREMY TODD, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
MARVIN FONSECA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GUEVARA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/18/2023 Conditional Approval GORDON ZUBER
Underground Mechanical 7/19/2023 Approved GORDON ZUBER
Excavation/Setback/Form/Re-Bar 7/26/2023 Corrections Issued GORDON ZUBER
Excavation/Setback/Form/Re-Bar 8/4/2023 Approved GORDON ZUBER
BUILDING-Rough-Frame 12/20/2023 Not Ready for Inspection DANIEL GUEVARA
ELECTRICAL-Rough 12/20/2023 Corrections Issued DANIEL GUEVARA
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Approved DANIEL GUEVARA
Green Building Rough 12/20/2023 Not Ready for Inspection DANIEL GUEVARA
PLUMBING-Rough 12/20/2023 Approved DANIEL GUEVARA
ELECTRICAL-Rough 2/27/2024 Approved DANIEL GUEVARA
HVAC-Rough 2/27/2024 Approved DANIEL GUEVARA
Interior/Exterior Lathing 3/13/2024 No Access for Inspection DANIEL GONZALEZ
Wood Frame 3/13/2024 No Access for Inspection DANIEL GONZALEZ
Wood Frame 3/14/2024 Corrections Issued DANIEL GONZALEZ
BUILDING-Rough-Frame 5/6/2024 Approved DANIEL GUEVARA
Green Building Rough 5/6/2024 Approved DANIEL GUEVARA
Interior/Exterior Lathing 5/6/2024 Approved DANIEL GUEVARA
PLUMBING-Rough 5/6/2024 Approved DANIEL GUEVARA
Insulation 5/8/2024 Approved DANIEL GUEVARA
Drywall Nailing 6/27/2024 Approved DANIEL GUEVARA
Interior/Exterior Lathing 6/27/2024 Approved DANIEL GUEVARA
Gas Test 9/12/2024 Corrections Issued DANIEL GUEVARA
ELECTRICAL-Final 3/18/2025 Not Ready for Inspection DANIEL GUEVARA
Service/Power Release 3/18/2025 Corrections Issued DANIEL GUEVARA
Service/Power Release 3/25/2025 Approved DANIEL GUEVARA
Service/Power Release 4/30/2025 Corrections Issued DANIEL GUEVARA
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved DANIEL GUEVARA
ELECTRICAL-Final 9/30/2025 Approved DANIEL GUEVARA
Final 9/30/2025 Conditional Approval DANIEL GUEVARA
Footing/Foundation/Slab 9/30/2025 Approved DANIEL GUEVARA
Green Building Final 9/30/2025 Approved DANIEL GUEVARA
HVAC-Final 9/30/2025 Approved DANIEL GUEVARA
PLUMBING-Final 9/30/2025 Approved DANIEL GUEVARA
Smoke Detectors 9/30/2025 Approved DANIEL GUEVARA