423-423 1/2 E 25TH ST 90011
Certificate Information: 423-423 1/2 E 25TH ST 90011
- Application / Permit
- 21014-20000-05389
- Plan Check / Job No.
- B21VN14743
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF A 390 SQ. FT. FOR A NEW ACCESSORY DWELLING UNIT ATTACHED TO EX. DWELLING PER LAMC 12.22 A.33(c) and (e). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/16/2023
- Issuing Office
- Metro
- Current Status
- Issued on 6/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | JEFFREY TANGONAN |
| Corrections Issued | 11/23/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 3/24/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Issued | 6/16/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2021 | ABEL CASILLAS |
| Permit | Cleared | 12/3/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/24/2022 | ABEL CASILLAS |
| Low Impact Development | Cleared | 6/8/2022 | SUNG JOON WON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16200 VENTURA BLVD SUITE 227 ENCINO, CA 91436 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/18/2023 | Conditional Approval | GORDON ZUBER |
| Underground Mechanical | 7/19/2023 | Approved | GORDON ZUBER |
| Excavation/Setback/Form/Re-Bar | 7/26/2023 | Corrections Issued | GORDON ZUBER |
| Excavation/Setback/Form/Re-Bar | 8/4/2023 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 12/20/2023 | Not Ready for Inspection | DANIEL GUEVARA |
| ELECTRICAL-Rough | 12/20/2023 | Corrections Issued | DANIEL GUEVARA |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Approved | DANIEL GUEVARA |
| Green Building Rough | 12/20/2023 | Not Ready for Inspection | DANIEL GUEVARA |
| PLUMBING-Rough | 12/20/2023 | Approved | DANIEL GUEVARA |
| ELECTRICAL-Rough | 2/27/2024 | Approved | DANIEL GUEVARA |
| HVAC-Rough | 2/27/2024 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 3/13/2024 | No Access for Inspection | DANIEL GONZALEZ |
| Wood Frame | 3/13/2024 | No Access for Inspection | DANIEL GONZALEZ |
| Wood Frame | 3/14/2024 | Corrections Issued | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 5/6/2024 | Approved | DANIEL GUEVARA |
| Green Building Rough | 5/6/2024 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 5/6/2024 | Approved | DANIEL GUEVARA |
| PLUMBING-Rough | 5/6/2024 | Approved | DANIEL GUEVARA |
| Insulation | 5/8/2024 | Approved | DANIEL GUEVARA |
| Drywall Nailing | 6/27/2024 | Approved | DANIEL GUEVARA |
| Interior/Exterior Lathing | 6/27/2024 | Approved | DANIEL GUEVARA |
| Gas Test | 9/12/2024 | Corrections Issued | DANIEL GUEVARA |
| ELECTRICAL-Final | 3/18/2025 | Not Ready for Inspection | DANIEL GUEVARA |
| Service/Power Release | 3/18/2025 | Corrections Issued | DANIEL GUEVARA |
| Service/Power Release | 3/25/2025 | Approved | DANIEL GUEVARA |
| Service/Power Release | 4/30/2025 | Corrections Issued | DANIEL GUEVARA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Approved | DANIEL GUEVARA |
| ELECTRICAL-Final | 9/30/2025 | Approved | DANIEL GUEVARA |
| Final | 9/30/2025 | Conditional Approval | DANIEL GUEVARA |
| Footing/Foundation/Slab | 9/30/2025 | Approved | DANIEL GUEVARA |
| Green Building Final | 9/30/2025 | Approved | DANIEL GUEVARA |
| HVAC-Final | 9/30/2025 | Approved | DANIEL GUEVARA |
| PLUMBING-Final | 9/30/2025 | Approved | DANIEL GUEVARA |
| Smoke Detectors | 9/30/2025 | Approved | DANIEL GUEVARA |