4555 N PLACIDIA AVE 91602
Certificate Information: 4555 N PLACIDIA AVE 91602
- Application / Permit
- 21014-20000-05383
- Plan Check / Job No.
- B21VN14724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 37.5' X 21.5', 10'X12.5' SECOND STORY ADDITION WITH A 6.5'X21'(N) PATIO COVER TO THE (E) SFD. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 12/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | PARISA ZAHABI |
| Corrections Issued | 11/25/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Applicant returned to address corrections | 2/18/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/6/2022 | JESSE ARELLANO |
| Issued | 12/8/2022 | APPLICANT |
| CofO in Progress | 5/3/2024 | DAVID MATSON |
| Permit Finaled | 5/3/2024 | RUBEN SALAS |
| CofO Issued | 5/3/2024 | RUBEN SALAS |
| Permit Finaled | 5/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/4/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/6/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | AMIR KASHFI |
| Low Impact Development | Cleared | 11/28/2022 | MARTIN FRAGOSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeo,, Stephen; Lic. No.: C65881 | 236 BRAXTONWOOD DR ANGIER, NC 27501 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/25/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/25/2023 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 4/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/23/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/23/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/23/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 6/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 6/23/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/23/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/30/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/30/2023 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 7/17/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/17/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | DAVID MATSON |
| Final | 3/27/2024 | Corrections Issued | DAVID MATSON |
| Green Building Final | 3/27/2024 | Approved | DAVID MATSON |
| Green Building Rough | 3/27/2024 | Approved | DAVID MATSON |
| MERV13>=Final | 3/27/2024 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 3/27/2024 | Approved | DAVID MATSON |
| Deputy Wood Construction | 5/3/2024 | Conditional Approval | DAVID MATSON |
| Final | 5/3/2024 | OK to Issue CofO | DAVID MATSON |
| MERV13>=Final | 5/3/2024 | Approved | DAVID MATSON |