13830-13832 W CANTLAY ST 91405

Certificate Information: 13830-13832 W CANTLAY ST 91405

Application / Permit
21014-20000-05376
Plan Check / Job No.
B21VN14707
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 29'8"X27'3" ACCESSORY DWELLING UNIT ADDITION TO EXISTING 1-STORY SFD W/ ATT GARAGE PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP. SEE COMMENTS. "The LID clearance has been deferred. Approval for LID requirments shall be obtained from LASAN prior to the issuace of the Certificate of Occupancy."
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
CofO Issued on 3/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2021 APPLICANT
Assigned to Plan Check Engineer 11/5/2021 HAYATO TSUCHIYA
Corrections Issued 11/7/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 1/4/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 4/21/2022 HAYATO TSUCHIYA
Plan Check Approved 5/10/2022 HAYATO TSUCHIYA
Building Plans Picked Up 5/10/2022 APPLICANT
Issued 5/19/2022 APPLICANT
CofO in Progress 2/28/2023 GREGG CUMMINGS
Permit Finaled 3/17/2023 MICHAEL SMITH
CofO Issued 3/17/2023 MICHAEL SMITH
Permit Finaled 3/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/12/2021 AMIR KASHFI
Sewer availability Cleared 11/12/2021 AMIR KASHFI
Address approval Cleared 12/7/2021 AMIR KASHFI
Roof/Waste drainage to street Cleared 5/6/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2022 Corrections Issued GREGG CUMMINGS
Pre-Inspection 7/1/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 7/18/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 7/18/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 8/1/2022 Corrections Issued GREGG CUMMINGS
Deputy Drilled-In Anchors 8/18/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 8/23/2022 Partial Approval DAVID MATSON
PLUMBING-Rough 8/23/2022 Partial Approval DAVID MATSON
Reinforced Concrete Frame 8/23/2022 Partial Approval DAVID MATSON
Sewer 8/23/2022 Partial Approval DAVID MATSON
Footing/Foundation/Slab 9/1/2022 Partial Approval WILLIAM WREN
Reinforced Concrete Frame 9/1/2022 Approved WILLIAM WREN
Deputy Drilled-In Anchors 9/2/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Rough 9/29/2022 Approved CLAYTON GRAHAM
Underground Mechanical 9/29/2022 Approved CLAYTON GRAHAM
Wood Frame 9/29/2022 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Rough 9/30/2022 Corrections Issued GREGG CUMMINGS
Wood Frame 9/30/2022 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Approval ALAN MORELOS
HVAC-Rough 10/13/2022 Partial Approval ALAN MORELOS
Wood Frame 10/13/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 10/20/2022 Approved GREGG CUMMINGS
Green Building Rough 10/20/2022 Approved GREGG CUMMINGS
HVAC-Rough 10/20/2022 Approved GREGG CUMMINGS
Insulation 10/20/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 10/20/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Approved WILLIAM WREN
Insulation 10/27/2022 Approved WILLIAM WREN
Underground Mechanical 10/27/2022 Not Ready for Inspection WILLIAM WREN
Drywall Nailing 11/2/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 11/9/2022 Partial Approval GREGG CUMMINGS
Underground Mechanical 11/9/2022 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 11/16/2022 Approved WILLIAM WREN
Shower Pan 11/16/2022 Approved WILLIAM WREN
Underground Mechanical 11/16/2022 Approved WILLIAM WREN
Final 1/9/2023 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 1/9/2023 Approved GREGG CUMMINGS
Green Building Final 1/9/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 1/9/2023 Approved GREGG CUMMINGS
Final 2/3/2023 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Not Ready GREGG CUMMINGS
Final 2/8/2023 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved GREGG CUMMINGS
ELECTRICAL-Final 2/21/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 2/21/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 2/21/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/21/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/27/2023 Approved GREGG CUMMINGS
Final 2/27/2023 OK to Issue CofO GREGG CUMMINGS