8117 S KENYON AVE 90045

Certificate Information: 8117 S KENYON AVE 90045

Application / Permit
21014-20000-05324
Plan Check / Job No.
B21VN14520
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 16'-11" x 32'-11" ADDITION AND INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING FOR A NEW BEDROOM, BATHROOM, CLOSET AND EXTEND (E) KITCHEN.
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 7/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/2/2021 SARKIS HARABEDIAN
Corrections Issued 11/4/2021 SARKIS HARABEDIAN
Plan Check Approved 12/2/2021 SARKIS HARABEDIAN
Issued 12/6/2021 APPLICANT
Building Plans Picked Up 12/8/2021 APPLICANT
CofO in Progress 7/21/2022 EVAN COOPER
Permit Finaled 7/28/2022 DANIEL ORRANTE
CofO Issued 7/28/2022 DANIEL ORRANTE
Permit Finaled 7/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/9/2021 PEDRO AYALA
Sewer availability Cleared 11/12/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/15/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 11/15/2021 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/19/2022 Approved BOBBY KEY
Special/Order Compliance 1/19/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval BOBBY KEY
Green Building Rough 2/22/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 2/22/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 2/28/2022 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Conditional Approval ANDREW NAVE
Deputy Wood Construction 3/16/2022 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Approved BOBBY KEY
HVAC-Rough 3/23/2022 Corrections Issued BOBBY KEY
HVAC-Rough 3/30/2022 Corrections Issued CLAYTON GRAHAM
Interior/Exterior Lathing 3/30/2022 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 3/30/2022 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 4/5/2022 Approved BOBBY KEY
HVAC-Rough 4/5/2022 Approved BOBBY KEY
Interior/Exterior Lathing 4/5/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 4/5/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 4/11/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 4/13/2022 Approved BOBBY KEY
Footing/Foundation/Slab 4/13/2022 Approved BOBBY KEY
Green Building Rough 4/13/2022 Approved BOBBY KEY
Insulation 4/18/2022 Conditional Approval JESUS RODRIGUEZ
Shower Pan 4/18/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 4/22/2022 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 4/22/2022 Not Ready for Inspection DAVID FEILER
Final 6/29/2022 Corrections Issued BOBBY KEY
Green Building Final 6/29/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 6/29/2022 Approved BOBBY KEY
Final 7/12/2022 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Not Ready BOBBY KEY
Final 7/18/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Not Ready JESUS RODRIGUEZ
Final 7/19/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Not Ready JESUS RODRIGUEZ
Final 7/21/2022 OK to Issue CofO EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Approved EVAN COOPER