13015 W CANTARA ST 91605
Certificate Information: 13015 W CANTARA ST 91605
- Application / Permit
- 21014-20000-05322
- Plan Check / Job No.
- B21VN14515
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH 2ND STORY ADDITION PER LAMC 12.22A33(C)-(D). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | COLIN LOREDO |
| Corrections Issued | 12/2/2021 | COLIN LOREDO |
| Quality Review Completed | 12/8/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Applicant returned to address corrections | 2/8/2022 | COLIN LOREDO |
| Plan Check Approved | 2/17/2022 | COLIN LOREDO |
| Issued | 2/28/2022 | APPLICANT |
| CofO in Progress | 6/1/2023 | GREGG CUMMINGS |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
| CofO Issued | 6/8/2023 | MICHAEL SMITH |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 1/15/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/18/2022 | JOSE DUARTE-DIAZ |
| Miscellaneous | Cleared | 2/10/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | 13302 FILMORE ST PACOIMA, CA 91331 |
| Engineer | Morales,, Carlos A; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 3/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/29/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 4/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 4/29/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 4/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 5/5/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/5/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 5/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 5/11/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Wood Frame | 5/12/2022 | Approved | DAVID MATSON |
| Insulation | 5/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/17/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/20/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 5/20/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 8/11/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | GREGG CUMMINGS |
| Final | 4/19/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/19/2023 | Approved | GREGG CUMMINGS |
| Green Building Final | 4/19/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 4/19/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 4/19/2023 | Approved | GREGG CUMMINGS |
| Final | 5/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 5/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 5/31/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/1/2023 | Approved | GREGG CUMMINGS |
| Final | 6/1/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 6/1/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 6/1/2023 | Approved | GREGG CUMMINGS |