6215 W GLEN OAK 90068
Certificate Information: 6215 W GLEN OAK 90068
- Application / Permit
- 21014-20000-05314
- Plan Check / Job No.
- B21VN14487
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL AND (24'-0"x16'-7"), 333 SQFT 2ND STORY ADDITION TO (E) SFD W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | PETER MOSESIAN |
| Corrections Issued | 11/20/2021 | PETER MOSESIAN |
| Quality Review Completed | 11/30/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| Plan Check Approved | 3/23/2022 | PETER MOSESIAN |
| Issued | 5/5/2022 | APPLICANT |
| CofO in Progress | 3/21/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 4/11/2023 | DEROLD HAUFF |
| CofO Issued | 4/11/2023 | DEROLD HAUFF |
| Permit Finaled | 4/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/20/2021 | ALEXANDER HELFER |
| Roof/Waste drainage to street | Cleared | 12/22/2021 | CELINA MORENO |
| Sewer availability | Cleared | 12/22/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | CELINA MORENO |
Contact Information
| Contractor | Trinity Builders & Design Inc; Lic. No.: 988119-B | 7022 DARBY AVE UNIT A RESEDA, CA 91335 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| Underground Mechanical | 8/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 8/15/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 8/15/2022 | Partial Approval | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 8/15/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 8/18/2022 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 9/20/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 10/13/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 10/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 10/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 11/7/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/7/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/10/2022 | Corrections Issued | RUBEN SALAS |
| Interior/Exterior Lathing | 12/2/2022 | Partial Approval | RUBEN SALAS |
| Shower Pan | 12/2/2022 | Approved | RUBEN SALAS |
| Wood Frame | 12/2/2022 | Approved | RUBEN SALAS |
| Insulation | 12/12/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 12/12/2022 | Approved | RUBEN SALAS |
| Drywall Nailing | 12/14/2022 | Approved | RUBEN SALAS |
| Green Building Rough | 12/14/2022 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 2/10/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 2/10/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 2/10/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 2/10/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 2/10/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | STUART CHAPMAN |
| Final | 3/9/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/9/2023 | Approved | STUART CHAPMAN |
| Green Building Final | 3/9/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 3/9/2023 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/9/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/20/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 3/20/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/20/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/20/2023 | Approved | JOAQUIN GREENOUGH |