17537 W BURBANK BLVD 91316
Certificate Information: 17537 W BURBANK BLVD 91316
- Application / Permit
- 21014-20000-05308
- Plan Check / Job No.
- B21VN14472
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 2-STORY ACCESSORY DWELLING UNIT TO (E) DET. GARAGE (43'-0"x30'-0" ) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 11/21/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 12/1/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| Applicant returned to address corrections | 5/4/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/24/2022 | MOHAMMAD ESMAILI |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 2/1/2024 | JON MCHUGH |
| Permit Finaled | 3/19/2024 | JOHN JANSON |
| CofO Issued | 3/19/2024 | JOHN JANSON |
| Permit Finaled | 3/19/2024 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/4/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/4/2022 | MARCO SANCHEZ |
| Address approval | Cleared | 4/18/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/19/2022 | CARLOS AGUILERA |
| ZI | Cleared | 6/1/2022 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/20/2023 | Not Ready for Inspection | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 6/5/2023 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 7/11/2023 | Partial Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 7/11/2023 | Corrections Issued | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 9/1/2023 | Approved | JON MCHUGH |
| Final | 9/1/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 11/3/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 11/3/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 11/3/2023 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 11/3/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 11/3/2023 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 11/13/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 11/13/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 11/13/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 11/13/2023 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 11/13/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 11/13/2023 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 11/17/2023 | Partial Approval | JON MCHUGH |
| Insulation | 11/17/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 11/17/2023 | Partial Approval | JON MCHUGH |
| Shower Pan | 11/17/2023 | Approved | JON MCHUGH |
| Wood Frame | 11/17/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 11/27/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 11/27/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 11/27/2023 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 1/29/2024 | Corrections Issued | JON MCHUGH |
| Final | 1/29/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 1/29/2024 | Approved | JON MCHUGH |
| Green Building Final | 1/29/2024 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 1/29/2024 | Approved | JON MCHUGH |
| HVAC-Final | 1/29/2024 | Approved | JON MCHUGH |
| MERV13>=Final | 1/29/2024 | Approved | JON MCHUGH |
| MERV13>=Rough | 1/29/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 1/29/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 1/29/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 2/1/2024 | Approved | JON MCHUGH |
| Final | 2/1/2024 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 2/1/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 2/1/2024 | Approved | JON MCHUGH |
| Special/Order Compliance | 3/11/2024 | Corrections Issued | JON MCHUGH |