24220 W HARTLAND ST 91307
Certificate Information: 24220 W HARTLAND ST 91307
- Application / Permit
- 21014-20000-05307
- Plan Check / Job No.
- B21VN14470
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 12' X 20' LIVING ROOM. 19'-8" X 49'-9" IRREG SHAPED ADDITION AND REMODEL TO ADD NEW BEDROOM AND BATHROOM, AND TO ENLARGE AND REMODEL KITCHEN AND LAUNDRY ROOM.
- Permit Issued
- Issued on 3/20/2022
- Issuing Office
- Current Status
- Issued on 3/20/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 10/31/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/2/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Issued | 3/20/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 12/20/2021 | AMIR KASHFI |
| Low Impact Development | Cleared | 2/9/2022 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 2/11/2022 | AMIR KASHFI |
Contact Information
| Architect | Armstrong,, James Edward; Lic. No.: C22059 | 2300 KNOLL DRIVE SUITE A VENTURA, CA 93003 |
| Contractor | Owner-Builder | , |
| Engineer | Putney,, Corrie Anne; Lic. No.: C54121 | 698 WESTFIELD CT VENTURA, CA 93004 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 4/14/2022 | Partial Approval | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 4/22/2022 | Approved | TROY SANDERS |
| Grounding or Bonding | 4/22/2022 | Approved | TROY SANDERS |
| Deputy Wood Construction | 5/25/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 6/28/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 6/28/2022 | Approved | TROY SANDERS |
| Green Building Rough | 6/28/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 6/28/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 6/28/2022 | Approved | TROY SANDERS |
| Insulation | 7/6/2022 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 7/6/2022 | Not Ready for Inspection | JESUS PINEDA |
| Shower Pan | 7/6/2022 | Not Ready for Inspection | JESUS PINEDA |
| Insulation | 7/8/2022 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 7/8/2022 | Corrections Issued | JESUS PINEDA |
| Insulation | 7/13/2022 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 7/13/2022 | Partial Approval | JESUS PINEDA |
| Shower Pan | 7/13/2022 | Not Ready for Inspection | JESUS PINEDA |
| Insulation | 7/18/2022 | Approved | JESUS PINEDA |
| Shower Pan | 7/18/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 7/21/2022 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/21/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 9/26/2023 | Approved | TROY SANDERS |
| Final | 9/26/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 9/26/2023 | Approved | TROY SANDERS |
| Green Building Rough | 9/26/2023 | Approved | TROY SANDERS |
| Grounding or Bonding | 9/26/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 9/26/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/26/2023 | Approved | TROY SANDERS |