7807-7809 S BREEN AVE 90045

Certificate Information: 7807-7809 S BREEN AVE 90045

Application / Permit
21014-20000-05288
Plan Check / Job No.
B21VN14417
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO (E) SINGLE FAMILY DWLLING, CONVERT (E) GARAGE INTO 2-STORY ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/3/2022
Issuing Office
Current Status
CofO Issued on 2/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 COLIN LOREDO
Corrections Issued 11/30/2021 COLIN LOREDO
Building Plans Picked Up 11/30/2021 APPLICANT
Quality Review Completed 1/20/2022 OMID HEDAYAT
Plan Check Approved 1/20/2022 COLIN LOREDO
Issued 2/3/2022 APPLICANT
CofO in Progress 2/16/2024 BOBBY KEY
Permit Finaled 2/17/2024 DANIEL ORRANTE
CofO Issued 2/17/2024 DANIEL ORRANTE
Permit Finaled 2/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 12/3/2021 STEVEN WECHSLER
Address approval Cleared 12/8/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 12/8/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 12/10/2021 SERGIO VALENZUELA
Eng Process Fee Ord 176,300 Cleared 12/20/2021 ANTHONY MAINEZ
Sewer availability Cleared 12/20/2021 ANTHONY MAINEZ

Contact Information

Contractor La Home Construction; Lic. No.: 1061118-B 8610 CHALMERS DR 203      LOS ANGELES, CA 90035
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/20/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 7/20/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 9/18/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 9/18/2023 Approved BOBBY KEY
HVAC-Rough 9/18/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 9/18/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 10/17/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 10/17/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Approved BOBBY KEY
HVAC-Rough 10/17/2023 Approved BOBBY KEY
PLUMBING-Rough 10/17/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 10/31/2023 Approved BOBBY KEY
ELECTRICAL-Rough 10/31/2023 Approved BOBBY KEY
Green Building Rough 10/31/2023 Approved BOBBY KEY
Insulation 10/31/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 10/31/2023 Approved BOBBY KEY
Shower Pan 10/31/2023 Approved BOBBY KEY
Insulation 11/6/2023 Partial Approval BOBBY KEY
Drywall Nailing 11/20/2023 Approved BOBBY KEY
ELECTRICAL-Final 1/31/2024 Corrections Issued BOBBY KEY
Final 1/31/2024 Corrections Issued BOBBY KEY
Green Building Final 1/31/2024 Approved BOBBY KEY
HVAC-Final 1/31/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 1/31/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 1/31/2024 Approved BOBBY KEY
ELECTRICAL-Final 2/13/2024 Approved BOBBY KEY
Final 2/13/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 2/13/2024 Approved BOBBY KEY
PLUMBING-Final 2/13/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Approved BOBBY KEY
Final 2/16/2024 OK to Issue CofO BOBBY KEY