7807-7809 S BREEN AVE 90045
Certificate Information: 7807-7809 S BREEN AVE 90045
- Application / Permit
- 21014-20000-05288
- Plan Check / Job No.
- B21VN14417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO (E) SINGLE FAMILY DWLLING, CONVERT (E) GARAGE INTO 2-STORY ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 2/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | COLIN LOREDO |
| Corrections Issued | 11/30/2021 | COLIN LOREDO |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| Quality Review Completed | 1/20/2022 | OMID HEDAYAT |
| Plan Check Approved | 1/20/2022 | COLIN LOREDO |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 2/16/2024 | BOBBY KEY |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
| CofO Issued | 2/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/3/2021 | STEVEN WECHSLER |
| Address approval | Cleared | 12/8/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 12/8/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 12/10/2021 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/20/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | La Home Construction; Lic. No.: 1061118-B | 8610 CHALMERS DR 203 LOS ANGELES, CA 90035 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/20/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 7/20/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 9/18/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/18/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 9/18/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 9/18/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 10/17/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 10/17/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/17/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 10/31/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/31/2023 | Approved | BOBBY KEY |
| Insulation | 10/31/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 10/31/2023 | Approved | BOBBY KEY |
| Shower Pan | 10/31/2023 | Approved | BOBBY KEY |
| Insulation | 11/6/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 11/20/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/31/2024 | Corrections Issued | BOBBY KEY |
| Final | 1/31/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 1/31/2024 | Approved | BOBBY KEY |
| HVAC-Final | 1/31/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 1/31/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 1/31/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/13/2024 | Approved | BOBBY KEY |
| Final | 2/13/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 2/13/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/13/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | BOBBY KEY |
| Final | 2/16/2024 | OK to Issue CofO | BOBBY KEY |