2135 W 74TH ST 90047
Certificate Information: 2135 W 74TH ST 90047
- Application / Permit
- 21014-20000-05273
- Plan Check / Job No.
- B21VN14364
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 2'-8" X 16'-1" PORTION OF GARAGE AND CONVERT REMAINING 9'-4" X 16'-1" DETACHED GARAGE AND ADD 30'-1" X 41'-9" IRREGULAR SHAPED TO CREATE 1186 SF (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/27/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/3/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 4/30/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Issued | 7/6/2022 | APPLICANT |
| CofO in Progress | 2/14/2025 | NICHOLAS LOPEZ |
| CofO Issued | 2/21/2025 | DEROLD HAUFF |
| Permit Finaled | 2/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/17/2022 | KHAING AYE |
| Address approval | Cleared | 3/18/2022 | KHOUNG LE |
| Roof/Waste drainage to street | Cleared | 3/18/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2022 | WALLIE JONG |
| Sewer availability | Cleared | 4/22/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/6/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/6/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/14/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 9/30/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/7/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/7/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 10/7/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/7/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/7/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/7/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 10/11/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/13/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/13/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/13/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/13/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/17/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/17/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 10/17/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/17/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/15/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/17/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 11/17/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/21/2022 | Approved | ENRIQUE MIRELES |
| Shower Pan | 11/21/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/24/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 3/24/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/7/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/7/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 7/7/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 7/7/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/7/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 7/7/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/4/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/7/2024 | Approved | ENRIQUE MIRELES |
| Final | 2/7/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 2/7/2024 | Approved | ENRIQUE MIRELES |
| MERV13>=Final | 2/7/2024 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/7/2024 | Approved | ENRIQUE MIRELES |
| Final | 2/9/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 2/26/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| Final | 2/11/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| Final | 2/14/2025 | OK to Issue CofO | NICHOLAS LOPEZ |