200 N GUNSTON DR 90049

Certificate Information: 200 N GUNSTON DR 90049

Application / Permit
21014-20000-05261
Plan Check / Job No.
B21VN14350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & 2-STORY ADDITION TO (E) 2-STORY SFD. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 8/16/2022
Issuing Office
Current Status
CofO Issued on 4/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 MARVEL DELACRUZ
Corrections Issued 11/30/2021 MARVEL DELACRUZ
Quality Review Completed 12/8/2021 STEVEN KIM
Applicant returned to address corrections 4/19/2022 RAPHAEL ROSAS
Applicant returned to address corrections 6/21/2022 RAPHAEL ROSAS
Applicant returned to address corrections 7/19/2022 RAPHAEL ROSAS
Applicant returned to address corrections 8/4/2022 RAPHAEL ROSAS
Plan Check Approved 8/9/2022 RAPHAEL ROSAS
Issued 8/16/2022 APPLICANT
Building Plans Picked Up 8/17/2022 APPLICANT
CofO in Progress 3/26/2025 CARLOS MATAMOROS
CofO Issued 4/9/2025 RICHARD STEINBACH
Permit Finaled 4/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Private street Cleared 12/2/2021 ANNA VIDAL
BHO/Hillside ordinance Cleared 12/7/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 12/7/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 12/7/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 12/7/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 12/7/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/13/2021 DINAH GARIN
Sewer availability Cleared 12/13/2021 DINAH GARIN
Excavation more than 5-ft deep Cleared 12/16/2021 CALOSHA APPROVED
Hydrant and Access approval Cleared 3/19/2022 DWIGHT SANKEY
Distance to fire station Cleared 4/5/2022 JOHN CONNEALLY
Low Impact Development Cleared 6/30/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/1/2022 SAUL GARCIA
GPI Written Notices Cleared 8/4/2022 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 8/4/2022 MARVEL DELACRUZ
Green Code Cleared 8/4/2022 MARVEL DELACRUZ

Contact Information

Architect Stockton,, Kenneth; Lic. No.: C19870 26500 W AGOURA RD. PMB # 844      CALABASAS, CA 91302
Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/9/2022 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/7/2022 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 12/8/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 12/29/2022 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/6/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/25/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 1/25/2023 Partial Approval CARLOS MATAMOROS
Deputy Wood Construction 1/26/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 2/13/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 2/15/2023 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 2/17/2023 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 3/4/2023 Off-Hour Fees Due
Masonry Wall/Backfill 3/4/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/7/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Masonry 3/7/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/9/2023 Partial Approval CARLOS MATAMOROS
Masonry Wall/Backfill 3/9/2023 Corrections Issued CARLOS MATAMOROS
Deputy Reinf. Masonry 3/14/2023 Conditional Approval CARLOS MATAMOROS
Pre-Inspection 3/14/2023 Approved CARLOS MATAMOROS
Masonry Wall/Backfill 3/18/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Masonry 3/24/2023 Conditional Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 3/24/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/11/2023 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/14/2023 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/18/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 4/22/2023 Off-Hour Fees Due
Underground Mechanical 4/22/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 5/3/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/3/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/23/2023 Partial Approval MICHAEL PELHAM
Underground Mechanical 5/23/2023 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/3/2023 Partial Approval JEREMY TODD
Deputy Drilled-In Anchors 6/23/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/26/2023 Partial Approval JESUS PINEDA
Deputy Reinf. Concrete 6/29/2023 Conditional Approval CARLOS MATAMOROS
PLUMBING-Rough 7/6/2023 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 7/6/2023 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 7/8/2023 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 7/13/2023 Partial Approval CARLOS MATAMOROS
Wood Frame 7/13/2023 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 7/14/2023 Partial Approval CARLOS MATAMOROS
Wood Frame 7/14/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 7/15/2023 Off-Hour Fees Due
Underground Mechanical 7/15/2023 Partial Approval CHRISTOPHER WILSON
Wood Frame 7/15/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 7/15/2023 Off-Hour Fees Due
Insulation 7/18/2023 Partial Approval CARLOS MATAMOROS
Wood Frame 7/18/2023 Corrections Issued CARLOS MATAMOROS
Insulation 7/19/2023 Partial Approval CARLOS MATAMOROS
Deputy Wood Construction 7/21/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Approved CARLOS MATAMOROS
Structural Steel Frame 7/21/2023 Not Ready for Inspection CARLOS MATAMOROS
Structural Steel Frame 8/4/2023 Approved CARLOS MATAMOROS
Deputy Wood Construction 8/9/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 8/18/2023 Partial Approval CARLOS MATAMOROS
Insulation 9/7/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 9/11/2023 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 9/13/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 9/13/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 9/13/2023 Not Ready for Inspection CARLOS MATAMOROS
Deputy Wood Construction 9/14/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Masonry 10/5/2023 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Approved CARLOS MATAMOROS
Special/Order Compliance 10/6/2023 Partial Inspection MICHAEL PELHAM
Masonry Wall/Backfill 10/7/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 10/7/2023 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 10/16/2023 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 10/20/2023 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 10/26/2023 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 11/7/2023 Partial Approval CARLOS MATAMOROS
HVAC-Rough 11/7/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 11/7/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 11/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval RICHARD STEINBACH
ELECTRICAL-Rough 11/14/2023 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 11/14/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 11/17/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 11/20/2023 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 11/27/2023 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 11/28/2023 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 12/1/2023 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 12/1/2023 Conditional Approval CARLOS MATAMOROS
Green Building Rough 12/1/2023 Partial Approval CARLOS MATAMOROS
MERV13>=Rough 12/1/2023 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 12/1/2023 Approved CARLOS MATAMOROS
Gas Test 12/2/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/2/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/2/2023 Off-Hour Fees Due
BUILDING-Rough-Frame 12/8/2023 Partial Approval CARLOS MATAMOROS
Green Building Rough 12/8/2023 Partial Approval CARLOS MATAMOROS
Insulation 12/8/2023 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 12/21/2023 Approved CARLOS MATAMOROS
Green Building Rough 12/21/2023 Approved CARLOS MATAMOROS
Wood Frame 12/21/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/22/2023 Approved CARLOS MATAMOROS
Insulation 12/28/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/28/2023 Partial Approval ARAM AVEDISIAN
Drywall Nailing 1/11/2024 Partial Approval CARLOS MATAMOROS
Shower Pan 1/16/2024 Approved CARLOS MATAMOROS
Drywall Nailing 1/24/2024 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 1/26/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 1/26/2024 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 1/26/2024 Partial Approval CARLOS MATAMOROS
Drywall Nailing 2/1/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 3/26/2024 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 4/1/2024 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 6/14/2024 Approved CARLOS MATAMOROS
Sewer 6/14/2024 Approved CARLOS MATAMOROS
Underground Mechanical 6/14/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 6/17/2024 Corrections Issued CARLOS MATAMOROS
Green Building Rough 6/17/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 6/20/2024 Approved CARLOS MATAMOROS
Insulation 6/20/2024 Approved CARLOS MATAMOROS
Gas Test 9/18/2024 Corrections Issued CARLOS MATAMOROS
Gas Test 9/19/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Final 12/23/2024 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 12/23/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Final 1/13/2025 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Final 1/27/2025 Approved CARLOS MATAMOROS
Final 1/27/2025 Corrections Issued CARLOS MATAMOROS
Green Building Final 1/27/2025 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Final 1/27/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 1/27/2025 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 1/29/2025 Not Required CARLOS MATAMOROS
Deputy Wood Construction 2/3/2025 Conditional Approval MICHAEL PELHAM
Final 2/25/2025 Partial Approval CARLOS MATAMOROS
Green Building Final 2/25/2025 Approved CARLOS MATAMOROS
Smoke Detectors 2/25/2025 Approved CARLOS MATAMOROS
Final 3/11/2025 Partial Approval CARLOS MATAMOROS
Final 3/18/2025 OK to Issue CofO CARLOS MATAMOROS