200 N GUNSTON DR 90049
Certificate Information: 200 N GUNSTON DR 90049
- Application / Permit
- 21014-20000-05261
- Plan Check / Job No.
- B21VN14350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 2-STORY ADDITION TO (E) 2-STORY SFD. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Current Status
- CofO Issued on 4/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | MARVEL DELACRUZ |
| Corrections Issued | 11/30/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 12/8/2021 | STEVEN KIM |
| Applicant returned to address corrections | 4/19/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/21/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/19/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/4/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 8/9/2022 | RAPHAEL ROSAS |
| Issued | 8/16/2022 | APPLICANT |
| Building Plans Picked Up | 8/17/2022 | APPLICANT |
| CofO in Progress | 3/26/2025 | CARLOS MATAMOROS |
| CofO Issued | 4/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Private street | Cleared | 12/2/2021 | ANNA VIDAL |
| BHO/Hillside ordinance | Cleared | 12/7/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/7/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/7/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/7/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/7/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 12/13/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 12/16/2021 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 3/19/2022 | DWIGHT SANKEY |
| Distance to fire station | Cleared | 4/5/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 6/30/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/1/2022 | SAUL GARCIA |
| GPI Written Notices | Cleared | 8/4/2022 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 8/4/2022 | MARVEL DELACRUZ |
| Green Code | Cleared | 8/4/2022 | MARVEL DELACRUZ |
Contact Information
| Architect | Stockton,, Kenneth; Lic. No.: C19870 | 26500 W AGOURA RD. PMB # 844 CALABASAS, CA 91302 |
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/7/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/8/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 1/6/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 1/25/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/25/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 1/26/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 2/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 2/15/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | CHRISTOPHER WILSON |
| Masonry Wall/Backfill | 3/4/2023 | Off-Hour Fees Due | |
| Masonry Wall/Backfill | 3/4/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/7/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Masonry | 3/7/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 3/9/2023 | Partial Approval | CARLOS MATAMOROS |
| Masonry Wall/Backfill | 3/9/2023 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Reinf. Masonry | 3/14/2023 | Conditional Approval | CARLOS MATAMOROS |
| Pre-Inspection | 3/14/2023 | Approved | CARLOS MATAMOROS |
| Masonry Wall/Backfill | 3/18/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Masonry | 3/24/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Masonry Wall/Backfill | 3/24/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/11/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/18/2023 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 4/22/2023 | Off-Hour Fees Due | |
| Underground Mechanical | 4/22/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 5/3/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/3/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/23/2023 | Partial Approval | MICHAEL PELHAM |
| Underground Mechanical | 5/23/2023 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/3/2023 | Partial Approval | JEREMY TODD |
| Deputy Drilled-In Anchors | 6/23/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/26/2023 | Partial Approval | JESUS PINEDA |
| Deputy Reinf. Concrete | 6/29/2023 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/6/2023 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 7/6/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 7/8/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Underground Mechanical | 7/13/2023 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 7/13/2023 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 7/14/2023 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 7/14/2023 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 7/15/2023 | Off-Hour Fees Due | |
| Underground Mechanical | 7/15/2023 | Partial Approval | CHRISTOPHER WILSON |
| Wood Frame | 7/15/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Wood Frame | 7/15/2023 | Off-Hour Fees Due | |
| Insulation | 7/18/2023 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 7/18/2023 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 7/19/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Wood Construction | 7/21/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Approved | CARLOS MATAMOROS |
| Structural Steel Frame | 7/21/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Structural Steel Frame | 8/4/2023 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 8/9/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/18/2023 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 9/7/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 9/11/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 9/13/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 9/13/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/13/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Wood Construction | 9/14/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Masonry | 10/5/2023 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 10/6/2023 | Partial Inspection | MICHAEL PELHAM |
| Masonry Wall/Backfill | 10/7/2023 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 10/7/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 10/16/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 10/20/2023 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/26/2023 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/7/2023 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 11/7/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/7/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 11/14/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Wood Frame | 11/14/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 11/17/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 11/20/2023 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 11/28/2023 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/1/2023 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 12/1/2023 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Rough | 12/1/2023 | Partial Approval | CARLOS MATAMOROS |
| MERV13>=Rough | 12/1/2023 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 12/2/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/2/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/2/2023 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 12/8/2023 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 12/8/2023 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 12/8/2023 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 12/21/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 12/21/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/22/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 12/28/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/28/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 1/11/2024 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 1/16/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 1/24/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/26/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 1/26/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/26/2024 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 2/1/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/26/2024 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 4/1/2024 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 6/14/2024 | Approved | CARLOS MATAMOROS |
| Sewer | 6/14/2024 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 6/14/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/17/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 6/17/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 6/20/2024 | Approved | CARLOS MATAMOROS |
| Gas Test | 9/18/2024 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 9/19/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 12/23/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 12/23/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/13/2025 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/27/2025 | Approved | CARLOS MATAMOROS |
| Final | 1/27/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Final | 1/27/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 1/27/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Service/Power Release | 1/29/2025 | Not Required | CARLOS MATAMOROS |
| Deputy Wood Construction | 2/3/2025 | Conditional Approval | MICHAEL PELHAM |
| Final | 2/25/2025 | Partial Approval | CARLOS MATAMOROS |
| Green Building Final | 2/25/2025 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/25/2025 | Approved | CARLOS MATAMOROS |
| Final | 3/11/2025 | Partial Approval | CARLOS MATAMOROS |
| Final | 3/18/2025 | OK to Issue CofO | CARLOS MATAMOROS |