4234 N EMPRESS AVE 91436

Certificate Information: 4234 N EMPRESS AVE 91436

Application / Permit
21014-20000-05254
Plan Check / Job No.
B21VN14278
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
199 SQ. FT. ADDITION OF A BATHROOM AND INTERIOR REMODEL TO THE (E) SFD. REMODEL THE KITCHEN, MASTER BATHROOM AND ADD TWO SKYLIGHTS.
Permit Issued
Issued on 4/11/2022
Issuing Office
Current Status
CofO Issued on 4/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2021 APPLICANT
Assigned to Plan Check Engineer 10/27/2021 MOHAMMAD ESMAILI
Corrections Issued 10/28/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 11/2/2021 APPLICANT
Plan Check Approved 3/10/2022 MOHAMMAD ESMAILI
Issued 4/11/2022 APPLICANT
CofO in Progress 4/10/2024 VINCENT HANLEY
Permit Finaled 4/12/2024 JOHN JANSON
CofO Issued 4/12/2024 JOHN JANSON
Permit Finaled 4/12/2024 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/23/2022 LAURINDA MEADE
Roof/Waste drainage to street Cleared 2/25/2022 CARLOS AGUILERA
Sewer availability Cleared 2/25/2022 CARLOS AGUILERA
Distance to fire station Cleared 2/28/2022 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 2/28/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 3/10/2022 MOHAMMAD ESMAILI

Contact Information

Contractor Benlian Bros Construction Inc; Lic. No.: 704254-B 11715 ANDREW AVENUE      GRANADA HILLS, CA 91344
Engineer Ekmekji,, Steve Eli; Lic. No.: C66727 19281 BERCLAIR LANE      TARZANA, CA 91356

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/10/2022 Approved DAVID SANDOVAL
Deputy Drilled-In Anchors 6/7/2022 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 10/12/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/7/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 12/7/2022 Approved VINCENT HANLEY
HVAC-Rough 12/7/2022 Approved VINCENT HANLEY
PLUMBING-Rough 12/7/2022 Approved VINCENT HANLEY
Wood Frame 12/7/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/20/2023 Approved JESUS PINEDA
Green Building Rough 1/20/2023 Approved JESUS PINEDA
Insulation 1/20/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 1/20/2023 Partial Approval JESUS PINEDA
Drywall Nailing 2/6/2023 Approved JESUS PINEDA
Shower Pan 2/6/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 2/15/2023 Approved VINCENT HANLEY
Final 8/29/2023 Corrections Issued VINCENT HANLEY
Green Building Final 8/29/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Approved VINCENT HANLEY
Smoke Detectors 8/29/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 9/15/2023 Approved VINCENT HANLEY
Final 9/15/2023 Corrections Issued VINCENT HANLEY
HVAC-Final 9/15/2023 Approved VINCENT HANLEY
PLUMBING-Final 9/15/2023 Approved VINCENT HANLEY
Final 9/21/2023 Corrections Issued VINCENT HANLEY
Final 4/9/2024 OK to Issue CofO VINCENT HANLEY