4234 N EMPRESS AVE 91436
Certificate Information: 4234 N EMPRESS AVE 91436
- Application / Permit
- 21014-20000-05254
- Plan Check / Job No.
- B21VN14278
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 199 SQ. FT. ADDITION OF A BATHROOM AND INTERIOR REMODEL TO THE (E) SFD. REMODEL THE KITCHEN, MASTER BATHROOM AND ADD TWO SKYLIGHTS.
- Permit Issued
- Issued on 4/11/2022
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/28/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| Plan Check Approved | 3/10/2022 | MOHAMMAD ESMAILI |
| Issued | 4/11/2022 | APPLICANT |
| CofO in Progress | 4/10/2024 | VINCENT HANLEY |
| Permit Finaled | 4/12/2024 | JOHN JANSON |
| CofO Issued | 4/12/2024 | JOHN JANSON |
| Permit Finaled | 4/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/23/2022 | LAURINDA MEADE |
| Roof/Waste drainage to street | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Distance to fire station | Cleared | 2/28/2022 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 3/10/2022 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Benlian Bros Construction Inc; Lic. No.: 704254-B | 11715 ANDREW AVENUE GRANADA HILLS, CA 91344 |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: C66727 | 19281 BERCLAIR LANE TARZANA, CA 91356 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/10/2022 | Approved | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 6/7/2022 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 10/12/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/7/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/7/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 12/7/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/7/2022 | Approved | VINCENT HANLEY |
| Wood Frame | 12/7/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 1/20/2023 | Approved | JESUS PINEDA |
| Insulation | 1/20/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 1/20/2023 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 2/6/2023 | Approved | JESUS PINEDA |
| Shower Pan | 2/6/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/15/2023 | Approved | VINCENT HANLEY |
| Final | 8/29/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/29/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 8/29/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/15/2023 | Approved | VINCENT HANLEY |
| Final | 9/15/2023 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 9/15/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/15/2023 | Approved | VINCENT HANLEY |
| Final | 9/21/2023 | Corrections Issued | VINCENT HANLEY |
| Final | 4/9/2024 | OK to Issue CofO | VINCENT HANLEY |