6033 N CASE AVE 91606
Certificate Information: 6033 N CASE AVE 91606
- Application / Permit
- 21014-20000-05248
- Plan Check / Job No.
- B21VN14264
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: 594 SQ.FT. (GROSS, WALLS INCLUDED) REC-ROOM CONVERSION TO ACCESSORY DWELLING UNIT PER STATE LAW
- Permit Issued
- Issued on 1/31/2022
- Issuing Office
- Current Status
- CofO Issued on 6/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2021 | CARLOS MONTES |
| Corrections Issued | 10/27/2021 | CARLOS MONTES |
| Plan Check Approved | 1/19/2022 | CARLOS MONTES |
| Issued | 1/31/2022 | APPLICANT |
| CofO in Progress | 5/31/2022 | MATT KELLERMAN |
| CofO in Progress | 5/31/2022 | MATT KELLERMAN |
| CofO Issued | 6/4/2022 | MICHAEL SMITH |
| Permit Finaled | 6/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/9/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/2/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Gas Test | 3/2/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/2/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/2/2022 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 3/2/2022 | Approved | JACK KARGODORIAN |
| Sewer | 3/2/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 3/2/2022 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/3/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/3/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/3/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/3/2022 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 3/3/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 3/4/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 3/10/2022 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 3/18/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/13/2022 | Approved | JACK KARGODORIAN |
| Final | 4/13/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/13/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 4/13/2022 | Approved | JACK KARGODORIAN |
| Final | 5/18/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 5/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 5/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 5/27/2022 | OK to Issue CofO | MATT KELLERMAN |
| Green Building Final | 5/27/2022 | Approved | MATT KELLERMAN |
| Service/Power Release | 5/27/2022 | Approved | MATT KELLERMAN |