16950 W KESWICK ST 91406
Certificate Information: 16950 W KESWICK ST 91406
- Application / Permit
- 21014-20000-05217
- Plan Check / Job No.
- B21VN14184
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19'6" X 16' 8" ADDITION OF A PATIO COVER TO THE (E) SFD. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2021 | PINANK PATEL |
| Corrections Issued | 10/19/2021 | PINANK PATEL |
| Plan Check Approved | 12/3/2021 | PINANK PATEL |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| Issued | 12/9/2021 | APPLICANT |
| CofO in Progress | 4/18/2023 | RAUL OLAGI |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
| CofO Issued | 4/19/2023 | MICHAEL SMITH |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/10/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/15/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/22/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/23/2023 | Not Ready for Inspection | RAUL OLAGI |
| Final | 3/23/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/23/2023 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Final | 3/23/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 3/23/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 3/23/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | RAUL OLAGI |
| Final | 4/18/2023 | OK to Issue CofO | RAUL OLAGI |
| Footing/Foundation/Slab | 4/18/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/18/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 4/18/2023 | Approved | RAUL OLAGI |