836 S MUIRFIELD ROAD 90005
Certificate Information: 836 S MUIRFIELD ROAD 90005
- Application / Permit
- 21014-20000-05209
- Plan Check / Job No.
- B21VN14150
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 1-STORY ADDITION TO (E) SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 4/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | COLIN LOREDO |
| Corrections Issued | 11/2/2021 | COLIN LOREDO |
| Quality Review Completed | 11/2/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| Applicant returned to address corrections | 1/26/2022 | COLIN LOREDO |
| Plan Check Approved | 3/8/2022 | COLIN LOREDO |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 4/3/2023 | JEFFREY MEAD |
| CofO Issued | 4/7/2023 | DEROLD HAUFF |
| Permit Finaled | 4/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/9/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 28411 ASCENT WAY SANTA CLARITA, CA 91350 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/7/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 4/7/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 4/7/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Pre-Inspection | 4/7/2022 | Partial Inspection | LILIANA PORTILLO |
| Special/Order Compliance | 4/7/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Final | 4/12/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/12/2022 | Conditional Approval | STUART CHAPMAN |
| METHANE-Subgrade | 4/12/2022 | Approved | STUART CHAPMAN |
| Insulation | 5/10/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 5/10/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Wood Frame | 5/10/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 5/12/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 6/21/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/13/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/13/2022 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 7/13/2022 | Partial Approval | JEFFREY MEAD |
| Wood Frame | 7/13/2022 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/18/2022 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 7/18/2022 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 7/18/2022 | Partial Approval | JEFFREY MEAD |
| Insulation | 8/1/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/1/2022 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 8/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 8/5/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 10/17/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Special/Order Compliance | 10/18/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 10/18/2022 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| Drywall Nailing | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| Final | 3/2/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| Green Building Rough | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| HVAC-Final | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| METHANE-Final | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| METHANE-Rough | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/2/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 3/2/2023 | No Access for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/22/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 3/22/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 3/22/2023 | Approved | JEFFREY MEAD |
| Final | 3/22/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 3/22/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 3/22/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 3/22/2023 | Approved | JEFFREY MEAD |
| METHANE-Final | 3/22/2023 | Approved | JEFFREY MEAD |
| METHANE-Rough | 3/22/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 3/22/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 3/22/2023 | Approved | JEFFREY MEAD |
| Final | 4/3/2023 | OK to Issue CofO | JEFFREY MEAD |