10033 N GLORIA AVE 91343

Certificate Information: 10033 N GLORIA AVE 91343

Application / Permit
21014-20000-05198
Plan Check / Job No.
B21VN14110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE AND ADD 16' X 24' TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 2/11/2022
Issuing Office
Current Status
CofO Issued on 7/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 RAPHAEL ROSAS
Corrections Issued 10/23/2021 RAPHAEL ROSAS
Issued 2/11/2022 APPLICANT
Building Plans Picked Up 2/22/2022 APPLICANT
CofO in Progress 7/18/2022 DEANDRE HOFFMAN
Permit Finaled 7/18/2022 MICHAEL SMITH
CofO Issued 7/18/2022 MICHAEL SMITH
Permit Finaled 7/18/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/5/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 11/5/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/10/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 11/17/2021 TIMOTHY POWELL
Eng Process Fee Ord 176,300 Cleared 12/8/2021 ROSE MARIE SMITH
Construction near power lines Cleared 1/22/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/31/2022 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 4/1/2022 Conditional Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 4/11/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 4/11/2022 Approved RAUL OLAGI
Sewer 4/11/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/25/2022 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Approved JAVIER RAMOS JR
Gas Test 4/25/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 4/25/2022 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 4/25/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 5/3/2022 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 5/10/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/10/2022 Corrections Issued JAVIER RAMOS JR
Green Building Rough 5/10/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 5/10/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/10/2022 Approved JAVIER RAMOS JR
Shower Pan 5/10/2022 Approved JAVIER RAMOS JR
Underground Mechanical 5/10/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/23/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 5/23/2022 Approved JAVIER RAMOS JR
Green Building Rough 5/23/2022 Approved JAVIER RAMOS JR
Insulation 5/23/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/23/2022 Partial Approval JAVIER RAMOS JR
Underground Mechanical 5/23/2022 Approved JAVIER RAMOS JR
Drywall Nailing 5/27/2022 Approved JAVIER RAMOS JR
Final 7/7/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/7/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/7/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/11/2022 Approved DEANDRE HOFFMAN
HVAC-Final 7/11/2022 Approved DEANDRE HOFFMAN
PLUMBING-Final 7/11/2022 Approved DEANDRE HOFFMAN
Service/Power Release 7/11/2022 Not Ready for Inspection DEANDRE HOFFMAN
Final 7/14/2022 OK to Issue CofO DEANDRE HOFFMAN
Service/Power Release 7/14/2022 Approved DEANDRE HOFFMAN