7823 S YORKTOWN AVE 90045
Certificate Information: 7823 S YORKTOWN AVE 90045
- Application / Permit
- 21014-20000-05195
- Plan Check / Job No.
- B21VN14090
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO 2-STORY ADU WITH ROOF DECK, (35'-2"x 20'-9"), 878 SQFT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/11/2021 | PETER MOSESIAN |
| Corrections Issued | 11/15/2021 | PETER MOSESIAN |
| Quality Review Completed | 11/23/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| Plan Check Approved | 1/27/2023 | PETER MOSESIAN |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 9/24/2024 | BOBBY KEY |
| CofO Issued | 9/25/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/25/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 12/2/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | DENNIS BRAGIN |
| Specific Plan | Cleared | 10/11/2022 | VALERIA CEJA |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 10/18/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 1/19/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Factor Vladimir; Lic. No.: 1046228-B | 22647 VENTURA BLVD #272 WOODLAND HILLS, CA 91364 |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/7/2023 | Partial Inspection | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 2/21/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 2/21/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/21/2023 | Partial Approval | BOBBY KEY |
| Sewer | 2/21/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 3/6/2023 | Approved | BOBBY KEY |
| Structural Steel Frame | 3/6/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 3/14/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/24/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 4/3/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 4/10/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 4/10/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 4/10/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/10/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 4/14/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 4/14/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 4/19/2023 | Approved | BOBBY KEY |
| Insulation | 4/19/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 4/21/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | BOBBY KEY |
| Green Building Rough | 4/28/2023 | Approved | BOBBY KEY |
| Insulation | 4/28/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/28/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 5/3/2023 | Approved | KENNETH NAGLE |
| Final | 5/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 5/17/2023 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Final | 9/9/2024 | Corrections Issued | BOBBY KEY |
| Final | 9/9/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/9/2024 | Approved | BOBBY KEY |
| HVAC-Final | 9/9/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/9/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/9/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/19/2024 | Not Ready for Inspection | BOBBY KEY |
| Final | 9/19/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 9/19/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 9/19/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | SGSOV Not Ready | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Not Ready | BOBBY KEY |
| Final | 9/24/2024 | OK to Issue CofO | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Approved | BOBBY KEY |