1310 1/2 W 41ST PL 90037

Certificate Information: 1310 1/2 W 41ST PL 90037

Application / Permit
21014-20000-05187
Plan Check / Job No.
B21VN14065
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE.
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 8/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 MICHAEL LOPEZ
Corrections Issued 11/26/2021 MICHAEL LOPEZ
Quality Review Completed 11/29/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/20/2022 MICHAEL LOPEZ
Applicant returned to address corrections 2/23/2022 MICHAEL LOPEZ
Plan Check Approved 4/6/2022 MICHAEL LOPEZ
Issued 4/13/2022 APPLICANT
CofO in Progress 7/31/2024 SABAS ALONSO
Permit Finaled 8/21/2024 RONALD MYRICK
CofO Issued 8/21/2024 RONALD MYRICK
Permit Finaled 8/21/2024 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/6/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 12/10/2021 KHOUNG LE
Sewer availability Cleared 12/10/2021 KHOUNG LE
Low Impact Development Cleared 3/7/2022 TA ANH
Roof/Waste drainage to street Cleared 3/9/2022 KHOUNG LE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 4/28/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 6/6/2022 Approved SABAS ALONSO
HVAC-Rough 6/6/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/6/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/9/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Approved SABAS ALONSO
Green Building Rough 6/9/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 6/9/2022 Approved SABAS ALONSO
Insulation 6/14/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 6/14/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 6/24/2022 Partial Approval HORACE FULTZ
Drywall Nailing 6/28/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 7/18/2022 Approved SABAS ALONSO
Shower Pan 7/18/2022 Partial Approval SABAS ALONSO
Special/Order Compliance 7/18/2022 Not Ready for Inspection HORACE FULTZ
Interior/Exterior Lathing 7/22/2022 Approved SABAS ALONSO
Shower Pan 7/22/2022 Approved SABAS ALONSO
Underground Mechanical 9/15/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Final 11/23/2022 Approved JAMES CHAVEZ
HVAC-Final 11/23/2022 Approved JAMES CHAVEZ
PLUMBING-Final 11/23/2022 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 6/15/2023 Not Ready for Inspection STUART CHAPMAN
Final 6/15/2023 Not Ready for Inspection STUART CHAPMAN
Green Building Final 6/15/2023 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 6/15/2023 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 6/15/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 10/30/2023 Not Ready for Inspection CRAIG DAVIS
Final 10/30/2023 No Access for Inspection CRAIG DAVIS
Green Building Final 10/30/2023 Not Ready for Inspection CRAIG DAVIS
Service/Power Release 10/30/2023 No Access for Inspection CRAIG DAVIS
Smoke Detectors 10/30/2023 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 11/1/2023 Approved SABAS ALONSO
Final 11/1/2023 Corrections Issued SABAS ALONSO
Green Building Final 11/1/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 11/1/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Approved SABAS ALONSO
Service/Power Release 11/1/2023 Corrections Issued SABAS ALONSO
Smoke Detectors 11/1/2023 Approved SABAS ALONSO
Final 1/31/2024 Corrections Issued SABAS ALONSO
Final 7/26/2024 Corrections Issued SABAS ALONSO
Final 7/30/2024 OK to Issue CofO SABAS ALONSO