14731 W KILLION ST 91411

Certificate Information: 14731 W KILLION ST 91411

Application / Permit
21014-20000-05180
Plan Check / Job No.
B21VN14040
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14' X 35'-9" ADDITION TO THE (E) SFD.
Permit Issued
Issued on 7/11/2022
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 SERGIO MUNIZ
Corrections Issued 10/25/2021 SERGIO MUNIZ
Applicant returned to address corrections 4/19/2022 SERGIO MUNIZ
Applicant returned to address corrections 5/19/2022 SERGIO MUNIZ
Plan Check Approved 6/29/2022 SERGIO MUNIZ
Building Plans Picked Up 6/30/2022 APPLICANT
Issued 7/11/2022 APPLICANT
CofO in Progress 2/26/2026 MISAEL ESPARZA
Permit Finaled 3/13/2026 RUBEN SALAS
CofO Issued 3/13/2026 RUBEN SALAS
Permit Finaled 3/13/2026 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 11/1/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/2/2021 JOSE DUARTE-DIAZ
Low Impact Development Cleared 3/29/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 7/7/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/15/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 7/18/2022 Approved MATT KELLERMAN
PLUMBING-Rough 8/22/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Partial Approval JACK KARGODORIAN
Service/Power Release 10/3/2022 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 10/25/2022 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 11/1/2022 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Partial Approval CALEB MEISTER
ELECTRICAL-Rough 11/17/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 11/17/2022 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 11/22/2022 Partial Approval THOMAS FINNILA
Green Building Rough 11/22/2022 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 12/1/2022 Conditional Approval THOMAS FINNILA
Green Building Rough 12/1/2022 Partial Approval THOMAS FINNILA
Insulation 12/7/2022 Partial Approval THOMAS FINNILA
Drywall Nailing 12/16/2022 Not Ready for Inspection THOMAS FINNILA
Shower Pan 12/16/2022 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 12/20/2022 Approved MATTHEW NELSON
Drywall Nailing 12/22/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/22/2024 Approved JACK KARGODORIAN
Final 10/22/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 10/22/2024 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 10/22/2024 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 10/22/2024 Approved JACK KARGODORIAN
Final 4/1/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 4/1/2025 Not Ready for Inspection JACK KARGODORIAN
Final 1/13/2026 Corrections Issued MATTHEW NELSON
Green Building Final 1/13/2026 Corrections Issued MATTHEW NELSON
Final 1/23/2026 Not Ready for Inspection JACK KARGODORIAN
Green Building Final 1/23/2026 Partial Approval JACK KARGODORIAN
Final 2/17/2026 OK to Issue CofO MISAEL ESPARZA
Green Building Final 2/17/2026 Approved MISAEL ESPARZA
Service/Power Release 2/17/2026 Approved MISAEL ESPARZA