11955 W HATTERAS ST 91607

Certificate Information: 11955 W HATTERAS ST 91607

Application / Permit
21014-20000-05174
Plan Check / Job No.
B21VN14031
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(16'-0"x31'-0"),445 SQ. FT. ADDITION TO THE REAR OF (E) SFD.
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2021 APPLICANT
Assigned to Plan Check Engineer 10/18/2021 PETER MOSESIAN
Corrections Issued 10/19/2021 PETER MOSESIAN
Plan Check Approved 1/10/2022 PETER MOSESIAN
Issued 1/28/2022 APPLICANT
CofO in Progress 3/15/2023 JOHN HAYES
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/25/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/26/2021 LEE GUILBEAUX
Sewer availability Cleared 10/26/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2022 Corrections Issued MISAEL ESPARZA
Pre-Inspection 2/8/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 2/22/2022 Partial Approval THOMAS FINNILA
PLUMBING-Rough 2/22/2022 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Partial Approval MICHAEL TEMPLE
PLUMBING-Rough 3/1/2022 Corrections Issued MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/4/2022 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 3/7/2022 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 3/29/2022 Not Ready for Inspection DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Not Ready for Inspection DAVID MATSON
HVAC-Rough 3/29/2022 Not Ready for Inspection DAVID MATSON
Wood Frame 3/29/2022 Not Ready for Inspection DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Approved ARAM AVEDISIAN
HVAC-Rough 4/1/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 4/6/2022 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Rough 4/15/2022 Corrections Issued MATT KELLERMAN
HVAC-Rough 4/15/2022 Corrections Issued MATT KELLERMAN
Wood Frame 4/15/2022 Corrections Issued MATT KELLERMAN
ELECTRICAL-Rough 4/21/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 4/21/2022 Not Ready for Inspection CALEB MEISTER
Wood Frame 4/21/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 4/28/2022 Approved CALEB MEISTER
ELECTRICAL-Rough 4/28/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Approved CALEB MEISTER
Green Building Rough 4/28/2022 Approved CALEB MEISTER
HVAC-Rough 4/28/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 4/28/2022 Partial Approval CALEB MEISTER
MERV13>=Rough 4/28/2022 Approved CALEB MEISTER
Insulation 5/20/2022 Approved CALEB MEISTER
Drywall Nailing 5/26/2022 Approved CALEB MEISTER
Deputy Drilled-In Anchors 6/6/2022 Conditional Approval CALEB MEISTER
Deputy Drilled-In Anchors 8/1/2022 Conditional Approval MATT KELLERMAN
Shower Pan 8/11/2022 Approved JOHN HAYES
Interior/Exterior Lathing 8/31/2022 Approved CALEB MEISTER
ELECTRICAL-Final 11/4/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 11/4/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 11/4/2022 Not Ready for Inspection JOHN HAYES
Final 1/18/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 1/18/2023 Not Ready for Inspection JOHN HAYES
Green Building Final 1/18/2023 Approved JOHN HAYES
MERV13>=Final 1/18/2023 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/18/2023 Not Ready for Inspection JOHN HAYES
Final 2/7/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 2/7/2023 Not Ready for Inspection JOHN HAYES
MERV13>=Final 2/7/2023 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Not Ready JOHN HAYES
Smoke Detectors 2/7/2023 Not Ready for Inspection JOHN HAYES
Final 3/10/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 3/10/2023 Approved JOHN HAYES
MERV13>=Final 3/10/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 3/10/2023 Approved JOHN HAYES
Final 3/15/2023 OK to Issue CofO JOHN HAYES