19235 W NASHVILLE ST 91326

Certificate Information: 19235 W NASHVILLE ST 91326

Application / Permit
21014-20000-05173
Plan Check / Job No.
B21VN14023
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'-7"x13'-0"),165.92 SQ. FT. ADDITION OF A FRONT PORCH AND 1/2 BATH WITH INTERIOR REMODEL THROUGHOUT THE (E) SFD.
Permit Issued
Issued on 12/16/2021
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2021 APPLICANT
Assigned to Plan Check Engineer 10/18/2021 PETER MOSESIAN
Corrections Issued 10/18/2021 PETER MOSESIAN
Building Plans Picked Up 10/20/2021 APPLICANT
Applicant returned to address corrections 11/15/2021 PETER MOSESIAN
Issued 12/16/2021 APPLICANT
CofO in Progress 9/22/2022 JEFFREY PARD
CofO Issued 9/22/2022 JOHN JANSON
Permit Finaled 9/22/2022 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/21/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/25/2021 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 11/1/2021 PETER MOSESIAN
Hold Cleared 1/4/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/21/2021 Partial Approval JEFFREY PARD
Underground Mechanical 12/21/2021 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/30/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/30/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Approved DAVID SCANTLIN
Green Building Rough 3/30/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 3/30/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 3/30/2022 Approved DAVID SCANTLIN
Wood Frame 3/30/2022 Approved DAVID SCANTLIN
Insulation 4/5/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 4/5/2022 Approved JEFFREY PARD
Drywall Nailing 4/12/2022 Approved JEFFREY PARD
Green Building Rough 4/12/2022 Approved JEFFREY PARD
Final 8/18/2022 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 8/18/2022 Approved JEFFREY PARD
Green Building Final 8/18/2022 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 8/18/2022 Approved JEFFREY PARD
Final 8/24/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 8/24/2022 Approved JEFFREY PARD