10239 W AUTUMN LEAF CIR 90077

Certificate Information: 10239 W AUTUMN LEAF CIR 90077

Application / Permit
21014-20000-05143
Plan Check / Job No.
B21VN13949
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE (E) 4'-10.5" X 15'-5" FRONT PORCH AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 RAPHAEL ROSAS
Corrections Issued 11/8/2021 RAPHAEL ROSAS
Quality Review Completed 11/10/2021 STEVEN KIM
Building Plans Picked Up 11/12/2021 APPLICANT
Applicant returned to address corrections 6/13/2022 RAPHAEL ROSAS
Plan Check Approved 7/18/2022 RAPHAEL ROSAS
Issued 7/18/2022 APPLICANT
CofO in Progress 9/5/2023 BRENDAN LOONEY
Permit Finaled 9/12/2023 DANIEL ORRANTE
CofO Issued 9/12/2023 DANIEL ORRANTE
Permit Finaled 9/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/22/2021 ALEXANDER ANDREWS
Tract Map conditions Cleared 2/4/2022 STEVEN WECHSLER
Specific Plan Cleared 2/11/2022 OLGA AYALA
ZI Cleared 2/11/2022 OLGA AYALA
Roof/Waste drainage to street Cleared 3/3/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 3/9/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Bayani-Rad,, Padra; Lic. No.: C86320 15901 HAWTHORNE BLVD UNIT 220      LAWNDALE, CA 90260

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/16/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 12/28/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 12/29/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 2/17/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/17/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 2/21/2023 Conditional Approval MICHAEL PELHAM
Deputy Other (see comments) 2/21/2023 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 3/3/2023 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/3/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 3/7/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 3/7/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 3/7/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 3/13/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 3/13/2023 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 3/13/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 3/22/2023 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 3/22/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 8/15/2023 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 8/15/2023 Approved BRENDAN LOONEY
Green Building Final 8/15/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 8/15/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready BRENDAN LOONEY
Pre-Inspection 8/28/2023 Corrections Issued BRENDAN LOONEY
Final 9/1/2023 OK to Issue CofO BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved BRENDAN LOONEY