8653 N BALCOM AVE 91325

Certificate Information: 8653 N BALCOM AVE 91325

Application / Permit
21014-20000-05139
Plan Check / Job No.
B21VN13905
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) STORAGE AND (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d), ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/25/2022
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 LUISANGEL VALENZUELA
Corrections Issued 10/23/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/13/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 1/12/2022 SHAHEN AKELYAN
Issued 1/25/2022 APPLICANT
Building Plans Picked Up 1/26/2022 APPLICANT
CofO in Progress 9/8/2022 JAVIER RAMOS JR
CofO in Progress 9/8/2022 ROBERT GOLD
Permit Finaled 9/10/2022 MICHAEL SMITH
CofO Issued 9/10/2022 MICHAEL SMITH
Permit Finaled 9/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/29/2021 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 11/29/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 11/29/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/30/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/14/2022 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 2/24/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 3/2/2022 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/8/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 3/29/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 3/29/2022 Approved JAVIER RAMOS JR
Sewer 3/29/2022 Partial Approval JAVIER RAMOS JR
Underground Mechanical 3/29/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval JAVIER RAMOS JR
HVAC-Rough 4/1/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 4/1/2022 Not Ready for Inspection JAVIER RAMOS JR
Deputy Wood Construction 4/4/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/7/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Approved JAVIER RAMOS JR
Green Building Rough 4/7/2022 Approved JAVIER RAMOS JR
Insulation 4/7/2022 Corrections Issued JAVIER RAMOS JR
Shower Pan 4/7/2022 Approved JAVIER RAMOS JR
Drywall Nailing 4/18/2022 Corrections Issued JAVIER RAMOS JR
Insulation 4/18/2022 Approved JAVIER RAMOS JR
Drywall Nailing 6/7/2022 Approved JAVIER RAMOS JR
Final 6/7/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/7/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Gas Company JAVIER RAMOS JR
Smoke Detectors 6/7/2022 Approved JAVIER RAMOS JR
Final 6/14/2022 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 6/14/2022 Approved JAVIER RAMOS JR