7826 3/4 S CROCKER ST 90003
Certificate Information: 7826 3/4 S CROCKER ST 90003
- Application / Permit
- 21014-20000-05136
- Plan Check / Job No.
- B21VN13898
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 9' x 11'1" ADDITION AND CONVERT THE (E) 18'2" x 18'3" GARAGE TO A (N) ACCESSORY DWELLING UNIT PER ENGINEERING
- Permit Issued
- Issued on 1/27/2022
- Issuing Office
- Current Status
- CofO Issued on 9/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2021 | JEFFREY TANGONAN |
| Corrections Issued | 10/18/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 1/12/2022 | JEFFREY TANGONAN |
| Issued | 1/27/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 9/8/2023 | MICHAEL LEWIS |
| CofO Issued | 9/13/2023 | DEROLD HAUFF |
| Permit Finaled | 9/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2021 | STEVE MELGAR |
| Permit | Cleared | 10/26/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 11/3/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 12/16/2021 | ABEL CASILLAS |
| Tenant Habitability Plan | Cleared | 12/16/2021 | RICARDO BOHORQUEZ |
Contact Information
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/15/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/15/2022 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 6/8/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/23/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/1/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/1/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/9/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/17/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/24/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 8/24/2022 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/30/2022 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Approved | LILIANA PORTILLO |
| Insulation | 9/30/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/5/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/5/2022 | Approved | LILIANA PORTILLO |
| Insulation | 10/5/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/21/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 11/30/2022 | No Access for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 12/5/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 12/5/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/3/2023 | No Access for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 2/3/2023 | No Access for Inspection | LILIANA PORTILLO |
| Sewer | 2/3/2023 | No Access for Inspection | LILIANA PORTILLO |
| Sewer | 2/10/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 2/10/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 7/20/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 7/20/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 7/20/2023 | Approved | MICHAEL LEWIS |
| Final | 9/7/2023 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/7/2023 | SGSOV Approved | MICHAEL LEWIS |