14334 W MIRANDA ST 91401

Certificate Information: 14334 W MIRANDA ST 91401

Application / Permit
21014-20000-05135
Plan Check / Job No.
B21VN13893
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
24'-6" X 42' ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 JEROME MAGAT PALMA
Corrections Issued 10/23/2021 JEROME MAGAT PALMA
Plan Check Approved 12/9/2021 JEROME MAGAT PALMA
Building Plans Picked Up 12/10/2021 APPLICANT
Issued 2/14/2022 APPLICANT
CofO in Progress 12/1/2022 RYAN SALAZAR
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/2/2021 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 11/22/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 11/22/2021 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 12/2/2021 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/25/2022 Partial Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 3/3/2022 Approved ALAN MORELOS
Footing/Foundation/Slab 3/3/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 4/29/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 4/29/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 4/29/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 4/29/2022 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 4/29/2022 Partial Approval RICHARD DOCKUS
Wood Frame 4/29/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 5/3/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 5/3/2022 Approved RICHARD DOCKUS
Green Building Rough 5/3/2022 Approved RICHARD DOCKUS
HVAC-Rough 5/3/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 5/3/2022 Approved RICHARD DOCKUS
Insulation 5/10/2022 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 5/10/2022 Partial Approval RICHARD DOCKUS
Insulation 5/13/2022 Not Ready for Inspection RICHARD DOCKUS
Insulation 5/17/2022 Approved RICHARD DOCKUS
Drywall Nailing 5/19/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 6/1/2022 Approved RICHARD DOCKUS
Shower Pan 6/1/2022 Approved RICHARD DOCKUS
Gas Test 9/22/2022 Approved RICHARD DOCKUS
Green Building Final 9/22/2022 Approved RICHARD DOCKUS
PLUMBING-Final 9/22/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 9/22/2022 Approved RICHARD DOCKUS
Final 11/2/2022 Conditional Approval RICHARD DOCKUS
Final 11/30/2022 OK to Issue CofO RYAN SALAZAR