14332 W MIRANDA ST 91401
Certificate Information: 14332 W MIRANDA ST 91401
- Application / Permit
- 21014-20000-05121
- Plan Check / Job No.
- B21VN13825
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (17'-5" X 14'-6') TO (E) SFD FOR NEW BEDROOM AND BATHROOM. WORK PER WFPP.
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2021 | ROSENDO MEDINA |
| Corrections Issued | 10/23/2021 | ROSENDO MEDINA |
| Plan Check Approved | 12/7/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Issued | 2/8/2022 | APPLICANT |
| CofO in Progress | 12/1/2022 | RYAN SALAZAR |
| CofO Issued | 12/10/2022 | MICHAEL SMITH |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 11/22/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 11/22/2021 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/25/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 3/3/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/29/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/29/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 4/29/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 4/29/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 4/29/2022 | Approved | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 4/29/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/3/2022 | Partial Approval | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 5/3/2022 | Approved | RICHARD DOCKUS |
| Insulation | 5/13/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 5/19/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/1/2022 | Corrections Issued | RICHARD DOCKUS |
| Shower Pan | 6/1/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/6/2022 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 7/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 7/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/22/2022 | Approved | RICHARD DOCKUS |
| Final | 9/22/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Gas Test | 9/22/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 9/22/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 9/22/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 11/2/2022 | Conditional Approval | RICHARD DOCKUS |
| Smoke Detectors | 11/2/2022 | Approved | RICHARD DOCKUS |
| Final | 11/30/2022 | OK to Issue CofO | RYAN SALAZAR |