14332 W MIRANDA ST 91401

Certificate Information: 14332 W MIRANDA ST 91401

Application / Permit
21014-20000-05121
Plan Check / Job No.
B21VN13825
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (17'-5" X 14'-6') TO (E) SFD FOR NEW BEDROOM AND BATHROOM. WORK PER WFPP.
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 ROSENDO MEDINA
Corrections Issued 10/23/2021 ROSENDO MEDINA
Plan Check Approved 12/7/2021 ROSENDO MEDINA
Building Plans Picked Up 12/8/2021 APPLICANT
Issued 2/8/2022 APPLICANT
CofO in Progress 12/1/2022 RYAN SALAZAR
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2021 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 11/22/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 11/22/2021 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 3/3/2022 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/29/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 4/29/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 4/29/2022 Approved RICHARD DOCKUS
HVAC-Rough 4/29/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 4/29/2022 Approved RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 4/29/2022 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 5/3/2022 Partial Approval RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 5/3/2022 Approved RICHARD DOCKUS
Insulation 5/13/2022 Approved RICHARD DOCKUS
Drywall Nailing 5/19/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 6/1/2022 Corrections Issued RICHARD DOCKUS
Shower Pan 6/1/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/6/2022 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 7/14/2022 Partial Approval JENNIFER RABUCHIN
Special/Order Compliance 7/14/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/22/2022 Approved RICHARD DOCKUS
Final 9/22/2022 Not Ready for Inspection RICHARD DOCKUS
Gas Test 9/22/2022 Approved RICHARD DOCKUS
Green Building Final 9/22/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 9/22/2022 Corrections Issued RICHARD DOCKUS
Final 11/2/2022 Conditional Approval RICHARD DOCKUS
Smoke Detectors 11/2/2022 Approved RICHARD DOCKUS
Final 11/30/2022 OK to Issue CofO RYAN SALAZAR