1040 W 75TH ST 90044

Certificate Information: 1040 W 75TH ST 90044

Application / Permit
21014-20000-05117
Plan Check / Job No.
B21VN13810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6'-2" X 35'-10" ADDITION TO SINGLE FAMILY DWELLING TO ADD NEW BATHROOM, NEW CLOSET, REMODEL (E) BATHROOM, AND ENLARGE BEDROOM AND LAUNDRY ROOM.
Permit Issued
Issued on 1/11/2022
Issuing Office
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/15/2021 JEROME MAGAT PALMA
Corrections Issued 10/16/2021 JEROME MAGAT PALMA
Building Plans Picked Up 10/21/2021 APPLICANT
Plan Check Approved 11/8/2021 JEROME MAGAT PALMA
Issued 1/11/2022 APPLICANT
CofO in Progress 4/7/2023 LILIANA PORTILLO
Permit Finaled 4/11/2023 DEROLD HAUFF
CofO Issued 4/11/2023 DEROLD HAUFF
Permit Finaled 4/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/3/2021 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 11/3/2021 CHRISTOPHER ROCHA

Contact Information

Contractor R L Remodeling Inc; Lic. No.: 885032-B 22817 VENTURA BLVD #852      WOODLAND HILLS, CA 91364
Engineer Nirattisai,, Preston; Lic. No.: C85115 28411 ASCENT WAY      SANTA CLARITA, CA 91350

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2022 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 7/6/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 7/6/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Approved LILIANA PORTILLO
Deputy Wood Construction 8/18/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 8/23/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 8/23/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 8/23/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/29/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 8/29/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Approved LILIANA PORTILLO
Green Building Rough 8/29/2022 Approved LILIANA PORTILLO
Insulation 10/5/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 10/5/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 10/17/2022 Conditional Approval LILIANA PORTILLO
HVAC-Rough 10/17/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/17/2022 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 10/26/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/14/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/14/2023 Corrections Issued LILIANA PORTILLO
Final 2/14/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 2/14/2023 Approved LILIANA PORTILLO
Green Building Final 2/14/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 2/14/2023 Approved LILIANA PORTILLO
PLUMBING-Final 2/14/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 2/14/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 3/14/2023 Not Ready for Inspection LILIANA PORTILLO
Final 3/14/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 3/14/2023 Approved LILIANA PORTILLO
PLUMBING-Final 3/14/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 3/14/2023 Approved LILIANA PORTILLO
Final 3/28/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 4/6/2023 Approved LILIANA PORTILLO
Final 4/6/2023 OK to Issue CofO LILIANA PORTILLO