12600 W COLLINS ST 91607
Certificate Information: 12600 W COLLINS ST 91607
- Application / Permit
- 21014-20000-05114
- Plan Check / Job No.
- B21VN13805
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION'S TO (E) ONE STORY SFD A TOTAL OF 701.95 SF, ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- Issued on 1/25/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 10/18/2021 | LUISANGEL VALENZUELA |
| Issued | 1/25/2022 | APPLICANT |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/1/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/5/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/6/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/10/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 5/26/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | No Access for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 7/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 7/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 7/5/2022 | Corrections Issued | RAFAEL CORTES |
| Wood Frame | 7/22/2022 | Partial Approval | RAFAEL CORTES |
| BUILDING-Rough-Frame | 8/9/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Rough | 8/9/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Rough-Elec/Plmb/HVAC | 8/9/2022 | Corrections Issued | RAFAEL CORTES |
| Deputy Wood Construction | 8/15/2022 | Conditional Approval | CALEB MEISTER |
| HVAC-Rough | 8/15/2022 | Corrections Issued | ALAN MORELOS |
| Interior/Exterior Lathing | 8/15/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 8/15/2022 | Not Ready for Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 8/26/2022 | Approved | RAFAEL CORTES |
| HVAC-Rough | 8/26/2022 | Corrections Issued | RAFAEL CORTES |
| Insulation | 8/26/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 8/26/2022 | Approved | RAFAEL CORTES |
| BUILDING-Rough-Frame | 8/31/2022 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 8/31/2022 | Approved | RAFAEL CORTES |
| Drywall Nailing | 9/9/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 9/27/2022 | Approved | RAFAEL CORTES |
| Final | 12/2/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 12/2/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 12/2/2022 | Approved | ARAM AVEDISIAN |
| Final | 12/9/2022 | Corrections Issued | JACK KARGODORIAN |
| Final | 1/18/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 1/18/2023 | Approved | CHRISTOPHER DELLEFIELD |