16014 1/2 S AINSWORTH ST 90247

Certificate Information: 16014 1/2 S AINSWORTH ST 90247

Application / Permit
21014-20000-05103
Plan Check / Job No.
B21VN13787
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD TO 3'-8" X 6'-9" AND CONVERT GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/9/2022
Issuing Office
Valley
Current Status
CofO Corrected on 11/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 SELLA BENYAMIN
Corrections Issued 10/19/2021 SELLA BENYAMIN
Plan Check Approved 2/20/2022 SELLA BENYAMIN
Issued 3/9/2022 APPLICANT
CofO in Progress 2/6/2024 JAMES CHAVEZ
CofO Issued-Status Void 2/7/2024 ANSON MAGLASANG
Permit Finaled-Status Void 2/7/2024 ANSON MAGLASANG
Re-Activate Permit 11/27/2024 ANSON MAGLASANG
Permit Finaled 11/27/2024 ANSON MAGLASANG
CofO Corrected 11/27/2024 ANSON MAGLASANG
Permit Finaled 11/27/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/26/2021 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 10/26/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/29/2021 JOSE HERNANDEZ
Sewer availability Cleared 10/29/2021 JOSE HERNANDEZ

Contact Information

Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 6/21/2022 Partial Inspection JOHN KLARIN
Deputy Drilled-In Anchors 7/13/2022 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/14/2022 Corrections Issued JOHN KLARIN
Deputy Drilled-In Anchors 11/2/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 11/2/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 1/27/2023 Corrections Issued JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 1/30/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 4/11/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 4/11/2023 Approved JAMES CHAVEZ
Green Building Rough 4/11/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 4/11/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 4/11/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 7/19/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 7/19/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 8/1/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 8/1/2023 Approved JAMES CHAVEZ
Green Building Rough 8/1/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 8/1/2023 Partial Inspection JAMES CHAVEZ
Insulation 8/4/2023 Approved JAMES CHAVEZ
Drywall Nailing 8/9/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 8/9/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 9/20/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Not Ready JAMES CHAVEZ
Sewer 9/20/2023 Approved JAMES CHAVEZ
Underground Mechanical 9/20/2023 Approved JAMES CHAVEZ
Final 1/23/2024 Partial Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved JAMES CHAVEZ
Service/Power Release 1/23/2024 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 1/23/2024 Approved JAMES CHAVEZ
Final 2/6/2024 OK to Issue CofO JAMES CHAVEZ
Green Building Final 2/6/2024 Approved JAMES CHAVEZ