18641-18643 W RINGLING ST 91356
Certificate Information: 18641-18643 W RINGLING ST 91356
- Application / Permit
- 21014-20000-05101
- Plan Check / Job No.
- B21VN13780
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan check* Convert a portion of the existing 2-story SFD to attached ADU and addition New Attached open trellis,
- Permit Issued
- Issued on 2/15/2024
- Issuing Office
- Current Status
- Issued on 2/15/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 11/30/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/5/2021 | HERNAN ARREOLA |
| Plan Check Approved | 7/18/2022 | ARSALAN SHABESTARI |
| Issued | 2/15/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | LEE GUILBEAUX |
| Permit | Cleared | 1/6/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 2/28/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 4/1/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 5/11/2022 | ARSALAN SHABESTARI |
Contact Information
| Architect | Woodcraft,, Lawrence Albert; Lic. No.: NA23651 | , |
| Contractor | Lee Stucker Construction; Lic. No.: 408676-B | , |
| Engineer | Tan,, Henreik Steven; Lic. No.: NA65723 | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/12/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/18/2024 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 4/18/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 4/25/2024 | Corrections Issued | JOHN KIDWELL |
| Deputy Other (see comments) | 5/3/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 5/3/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/6/2024 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 5/7/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Steel/Welding | 5/13/2024 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/28/2024 | Corrections Issued | JOHN KIDWELL |
| ELECTRICAL-Rough | 5/28/2024 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Conditional Approval | JOHN KIDWELL |
| Green Building Rough | 5/28/2024 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 5/28/2024 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/3/2024 | Conditional Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 7/3/2024 | Approved | JOHN KIDWELL |
| HVAC-Rough | 7/3/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 7/3/2024 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/24/2024 | Approved | MORRIS JACKSON |
| Green Building Rough | 7/24/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/1/2024 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 8/5/2024 | Approved | JOHN KIDWELL |
| Insulation | 8/5/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 8/12/2024 | Partial Approval | JOHN KIDWELL |
| Sewer | 8/12/2024 | Partial Approval | JOHN KIDWELL |
| Special/Order Compliance | 8/12/2024 | Approved | SCOTT SOBEL |
| PLUMBING-Rough | 8/14/2024 | Partial Approval | JOHN KIDWELL |
| Sewer | 8/14/2024 | Approved | JOHN KIDWELL |
| Final | 11/20/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 11/20/2024 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 11/20/2024 | Approved | JOHN KIDWELL |
| Final | 2/10/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 2/10/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 2/10/2025 | SGSOV Approved | JOHN KIDWELL |
| Final | 3/21/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 3/21/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 5/14/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 5/14/2025 | Approved | JOHN KIDWELL |
| Final | 5/20/2025 | Corrections Issued | JOHN KIDWELL |
| Final | 6/27/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Special/Order Compliance | 8/14/2025 | Corrections Issued | JOHN KIDWELL |