18405-18407 W JOVAN ST 91335

Certificate Information: 18405-18407 W JOVAN ST 91335

Application / Permit
21014-20000-05100
Plan Check / Job No.
B21VN13778
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan Check* ATTACHED GARAGE CONVERSION FOR ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A)
Permit Issued
Issued on 11/9/2021
Issuing Office
Current Status
CofO Issued on 3/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2021 APPLICANT
Assigned to Plan Check Engineer 10/12/2021 MONICA RAMIREZ
Corrections Issued 10/12/2021 MONICA RAMIREZ
Applicant returned to address corrections 10/15/2021 MONICA RAMIREZ
Applicant returned to address corrections 10/19/2021 CARLOS MONTES
Plan Check Approved 11/1/2021 MONICA RAMIREZ
Issued 11/9/2021 APPLICANT
CofO in Progress 3/16/2022 ROBERT GOLD
Permit Finaled 3/23/2022 JOHN JANSON
CofO Issued 3/23/2022 JOHN JANSON
Permit Finaled 3/23/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/13/2021 CARLOS AGUILERA
Sewer availability Cleared 10/13/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/30/2021 Approved SEAN HAUPT
PLUMBING-Rough 12/7/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/22/2021 Approved SEAN HAUPT
ELECTRICAL-Rough 12/22/2021 Approved SEAN HAUPT
Gas Test 12/22/2021 Partial Approval SEAN HAUPT
Green Building Rough 12/22/2021 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 12/22/2021 Approved SEAN HAUPT
Special/Order Compliance 12/22/2021 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 12/30/2021 Approved JAVIER RAMOS JR
Shower Pan 12/30/2021 Approved JAVIER RAMOS JR
Green Building Rough 1/3/2022 Approved SEAN HAUPT
Insulation 1/3/2022 Approved SEAN HAUPT
Drywall Nailing 1/11/2022 Approved MORRIS JACKSON
Service/Power Release 1/25/2022 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 3/2/2022 Approved SEAN HAUPT
Final 3/2/2022 Corrections Issued SEAN HAUPT
Green Building Final 3/2/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 3/2/2022 Corrections Issued SEAN HAUPT
PLUMBING-Final 3/2/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 3/2/2022 Approved SEAN HAUPT
Final 3/14/2022 OK to Issue CofO ROBERT GOLD
Green Building Final 3/14/2022 Approved ROBERT GOLD